Attendees: Paul, Beth, Josh, Richard, Scott, Mark, Jessica, Saul, Bruce, Matthew, Song New Action Item: - Mark will review unsorted features from Wind River team and try to have them scheduled (WIP, Reviewed, but not scheduled yet.) - Song and Saul to follow on Scott Garman's M2 schedule conflict. (WIP, need to talk with Dave) - Paul to work with Jeremy and others to move 1598 forward. (WIP) - Paul to split feature 1566. Agenda: * Opens collection - 5 min (Song) * Yocto 1.1.1 point release update - 10 min (Josh) - Got the build out before Christmas, QA test passed. One outstanding issue. Have a promising solution now. Pulling together some other minor fixes. Need to talk with Beth - Scott: do we need to update manual? - Beth will setup a meeting with Josh and Scott to determine the next build for QA and possible doc changes. * Yocto 1.2 M2 status and major kernel/toolchain version lock - 10 min (Song/Bruce/Team) https://wiki.yoctoproject.org/wiki/Yocto_Project_v1.2_Status - 4th week of M2, next week we will have RC1. more than half of the features are in progress, some in patch review, some is lacking QA effort, about 40% still has no progress. Paul and ScottG's P1's are at risk. - Paul will split P1 feature 1655 into deliverables for both M2 and M3. - Master build is green by the new year's day. Integrating patches now. - bugs are in control with about 15 new bugs opened and about the same amount fixed after Christmas. - Major kernel version lock: Kernel - 3.2.x with RT release. Tool Chain - set with the versions now, gcc 4.6, minor patches possible, but no more major version change. - M2 release criteria review (Reviewed and updated on the wiki page) * Opens - 10 min - RP: email status: had a disaster over holiday, lost all emails, recovered most of them. Reponses were delayed.
* Action item Review - 5 min - Mark will review unsorted features from Wind River team and try to have them scheduled (WIP, Reviewed, but not scheduled yet.) - Song and Saul to follow on Scott Garman's M2 schedule conflict. (WIP, need to talk with Dave) - Paul to work with Jeremy and others to move 1598 forward. (WIP) * Team Sharing (shared some holiday stories, skip due to holidays) _______________________________________________ yocto mailing list yocto@yoctoproject.org https://lists.yoctoproject.org/listinfo/yocto