Attendees:
Paul, Beth, Josh, Richard, Scott, Mark, Jessica, Saul, Bruce, Matthew, Song
 
New Action Item:
- Mark will review unsorted features from Wind River team and try to have them 
scheduled (WIP, Reviewed, but not scheduled yet.)
- Song and Saul to follow on Scott Garman's M2 schedule conflict. (WIP, need to 
talk with Dave)
- Paul to work with Jeremy and others to move 1598 forward. (WIP)
- Paul to split feature 1566.
 
Agenda:
* Opens collection - 5 min (Song)
* Yocto 1.1.1 point release update - 10 min (Josh) 
  - Got the build out before Christmas, QA test passed. One outstanding issue. 
Have a promising solution now. Pulling together some other minor fixes. Need to 
talk with Beth
  - Scott: do we need to update manual? 
  - Beth will setup a meeting with Josh and Scott to determine the next build 
for QA and possible doc changes.
 
* Yocto 1.2 M2 status and major kernel/toolchain version lock - 10 min 
(Song/Bruce/Team)
https://wiki.yoctoproject.org/wiki/Yocto_Project_v1.2_Status 
  
  - 4th week of M2, next week we will have RC1. more than half of the features 
are in progress, some in patch review, some is lacking QA effort, about 40% 
still has no progress. Paul and ScottG's P1's are at risk. 
  - Paul will split P1 feature 1655 into deliverables for both M2 and M3.
  - Master build is green by the new year's day. Integrating patches now.
  - bugs are in control with about 15 new bugs opened and about the same amount 
fixed after Christmas. 
  - Major kernel version lock: Kernel - 3.2.x with RT release. Tool Chain - set 
with the versions now, gcc 4.6, minor patches possible, but no more major 
version change. 
  - M2 release criteria review (Reviewed and updated on the wiki page)
 
* Opens - 10 min 
     -  RP: email status: had a disaster over holiday, lost all emails, 
recovered most of them. Reponses were delayed.

* Action item Review - 5 min
- Mark will review unsorted features from Wind River team and try to have them 
scheduled (WIP, Reviewed, but not scheduled yet.)
- Song and Saul to follow on Scott Garman's M2 schedule conflict. (WIP, need to 
talk with Dave)
- Paul to work with Jeremy and others to move 1598 forward. (WIP)
 
* Team Sharing (shared some holiday stories, skip due to holidays)
_______________________________________________
yocto mailing list
yocto@yoctoproject.org
https://lists.yoctoproject.org/listinfo/yocto

Reply via email to