On 12/13/2010 03:53 AM, Tian, Kevin wrote:
Hi, owners,

Since M2 code frozen happened last week and now M2 test has been started, could 
owners
of each M2 sprint tasks update the latest status on the wiki?

https://wiki.yoctoproject.org/wiki/Yocto_1.0_Schedule

As Saul sent out earlier, we only accept bug fixes on M2 branch now. So if a 
given task has
not been done (WIP or on track), could you either move it into M3 or fill an 
updated date
when current one is past?

--M2SB--

"Distro Audit: Package Description/Summary completed", "WIP, Done by Dec 08" 
(Mark)
"Zypper/RPM (small writeup)", "WIP, Done by Dec 06" (Mark/Qing)
"oprofileUI", "WIP, done by Dec 10 " (Jessica)

--M2SC--
"Distro Audit: Licence Checksums ", "WIP, done by Dec 10 " (Saul)
Pending Patch is in distro Stage

"Zypper/RPM (upgrade to latest version)", "Starting, done by Dec 10" (Mark/Qing)
"push of all relevant Wind River patchs to Yocto ", "WIP, on track for completion by 
Dec 03 " (Mark)
"Tracing: blktrace and sysprof recipes ", "sysprof by Dec 03 " (Tom)

--M2SD--
"Yocto Installer for SDK Generator Installation functions support ", "WIP, done Dec 
09" (Jessica)
"Yocto Installer support for image-creator ", "WIP" (Jessica)

--M2SE--
"Zypper/RPM (integration design)", "slipped out from sprint D" (Mark/Qing)
"Distro Audit: Upgrades Completed (Phase1)", "WIP" (Saul)
Phase one status was best effort on the the update list, and I will have a summary later this week.

"Distro Audit: Src Checksums", "WIP, Done by Dec 9" (Saul)
All recipes now have SRC_URI Checksums, the checking work is part of the Fetch which is pending with Ke and Richard.

"enable KVM with qemu", "on track" (Saul/Edwin)
Done and in Master

"Performance Enhancement Completed", "on track being reviewed" 
(Saul/Dongxiao/Qing)
Code is being review by RP, and I think there is some questions about the usage of the hard links.

"User specified qemu config support", "on track for Dec 9" (Saul/Criping)
Not sure what the status of this is currently.

"SDK Version Control support in SDK generator installer", "on track" (Jessica)
"Tracing: Initial SystemTap recipe", "on track" (Tom)
"Documentation for swabber", "on track" (Alex)
"Defect triage process in public documented and implemented" (Saul)
Bug Triage Process is on the Public website, some images need to be updated and I now have the source for those, this can be independent from the release process.


Thanks
Kevin