Hi,

I am trying to limit a defined project by adding it to the resource quota set 
but I am not able to limit the users defined in the project to 2 slots at a 
time. We are able to run more than 2 jobs at a time.

Here IT_test is the project name. Can anyone correct me if there is anything 
wrong in the syntax


{
   name         test
   description  "limit users to 2 slots"
   enabled      TRUE
   limit        projects IT_test to slots=2
}

Regards,
Sudha
The information contained in this electronic message and any attachments to 
this message are intended for the exclusive use of the addressee(s) and may 
contain proprietary, confidential or privileged information. If you are not the 
intended recipient, you should not disseminate, distribute or copy this e-mail. 
Please notify the sender immediately and destroy all copies of this message and 
any attachments. WARNING: Computer viruses can be transmitted via email. The 
recipient should check this email and any attachments for the presence of 
viruses. The company accepts no liability for any damage caused by any virus 
transmitted by this email. www.wipro.com
_______________________________________________
users mailing list
users@gridengine.org
https://gridengine.org/mailman/listinfo/users

Reply via email to