I have a requirement that I'm not sure how to fulfill and was hoping to get some suggestions.

each job requires
8 cores on a single machine, 1 license and 128G of RAM (most of my execution hosts are 16 cores 256G RAM) 4 or more simulations jobs that must run at nearly the same time on any execution host.

if the resources to run all 4 or more jobs are not available or will not become available shortly, all of the jobs should pend until resources become available.

since these are very big jobs and must run at some point, how can I make sure that the resources do become available at the same time with out waisting resources?

Any input would be very helpful and appreciated.
Thanks
-Bob