Greetings all.
I have a requirement that I'm not sure how to fulfill and was hoping to
get some suggestions.
each job requires
8 cores on a single machine, 1 license and 128G of RAM (most of
my execution hosts are 16 cores 256G RAM)
4 or more simulations jobs that must run at nearly the same time on any
execution host.
if the resources to run all 4 or more jobs are not available or will not
become available shortly, all of the jobs should pend until resources
become available.
since these are very big jobs and must run at some point, how can I make
sure that the resources do become available at the same time with out
waisting resources?
Any input would be very helpful and appreciated.
Thanks
-Bob