This is probably more of a question for the XS forums but thought I'd get you alls perspective too. We are moving buildings and need to move our CS + XS hardware. What it the recommended way to do that?
I was thinking of the following steps: 1) stop the CS management server 2) pause/stop every VM using XenCenter (CS system VMs last?) 3) shutdown XS hosts 4) shutdown Management Server host (also NFS server) 5) move On the other end I would: 1) boot Management Server Host (make sure CS Management Server is stopped, and NFS is up) 2) boot XS hosts 3) Use XenCenter to start all VMs (CS system vms first?) 4) Start CS Management Server Anything I am missing? thanks, Carlos