Hi Yannong Huang,
You can create multiple routing tasks for checkin/review/QA process.
If you create multi-level BOM then the system automatically generated
dependent jobs and will be shown in the production run screen.

On Mon, Feb 6, 2023 at 11:42 AM yannong huang <[email protected]>
wrote:

> Hi community,
>
> We recently came across a prospect/customer request to display production
> runs generated from a MRP run into a Gantt chart. We extended the
> Manufacturing module with the Gantt Chart displaying feature. Enclosed is a
> screenshot of a scenario with a 3-layer BOM where the finished good premium
> table is made of a golden table, which in turn is made of a (normal) table,
> and which finally is made of raw materials like wood, nail and varnish. The
> scenario does not make a lot of sense but is merely meant for illustrating
> the ideas.
>
> We appreciate advices from the community on:
>
> 1. Does it make sense to incorporate the feature into the product? If yes,
> what would be an appropriate procedure for code checkin/review/QA?
>
> 2. Does it make sense to further incorporate a tree view feature to
> display the pegging logic with a chain of production runs (and embedded
> production run tasks) for a given sales order?
>
> Thanks,
> Yannong
>


-- 
Kind Regards,