larryi      01/06/20 21:42:10

  Modified:    .        RELEASE-PLAN-3.3
  Log:
  Update release plan to add Milestone 4 and adjust dates
  
  Revision  Changes    Path
  1.12      +21 -3     jakarta-tomcat/RELEASE-PLAN-3.3
  
  Index: RELEASE-PLAN-3.3
  ===================================================================
  RCS file: /home/cvs/jakarta-tomcat/RELEASE-PLAN-3.3,v
  retrieving revision 1.11
  retrieving revision 1.12
  diff -u -r1.11 -r1.12
  --- RELEASE-PLAN-3.3  2001/05/15 12:59:49     1.11
  +++ RELEASE-PLAN-3.3  2001/06/21 04:42:08     1.12
  @@ -80,9 +80,27 @@
           structure consistent with other Jakarta projects, i.e. use
           jakarta-tomcat-3.3-xxx.
   
  +Tomcat 3.3 Milestone 4 Release:
  +
  +     Code Freeze/Tag Date:   June 20, 2001 
  +     Release Manager:        Larry Isaacs 
  +
  +     This release contains a switch to using jakarta-tomcat-connectors 
  +     for some utility classes.  It also uses jakarta-tomcat-jasper 
  +     for building jasper34, which will be enabled as the default 
  +     JSP handler.  The internal "jasper33" will be enabled as the 
  +     default JSP handler for future releases of Tomcat 3.3. 
  +
  +     Known issues in order of priority: 
  +     1. Jasper34 needs to be stable. 
  +     2. Watchdog and internal test need to be passing all tests. 
  +     3. Build documentation need to be updated to document 
  +        new dependencies on jakarta-tomcat-connectors and 
  +        jakarta-tomcat-jasper. 
  +
   Tomcat 3.3 Beta 1:
   
  -     Code Freeze/Tag Date:   March 26, 2001
  +     Code Freeze/Tag Date:   July 11, 2001
        Release Manager:        Larry Isaacs
   
        No major change will be done after the Beta is build without a 
  @@ -119,7 +137,7 @@
   
   Tomcat 3.3 Beta 2:
   
  -     Code Freeze/Tag Date:   June 2, 2001
  +     Code Freeze/Tag Date:   July 18, 2001
        Release Manager:        Larry Isaacs
   
        This release should fix any major bugs found in the 
  @@ -131,7 +149,7 @@
   
   Tomcat 3.3 Final Release
   
  -     Code Freeze Date:       June 9, 2001
  +     Code Freeze Date:       August 1, 2001
        Release Manager:        Larry Isaacs
   
        The final build. The pre-requisite for the release is having no bugs in
  
  
  

Reply via email to