Was checking mails I sent, and wanted to get back to this one in case
someone gets the same question.
We found out that the reason why we saw stages being complete without all
tasks complete is related to issues in the ListenerBus
We had to tune the event queue size, see this
https://issues.apach
Well, what's happening here is that jobs become "un-finished" - they
complete, and then later on pop back into the "Active" section showing a
small number of complete/inprogress tasks.
In my screenshot, Job #1 completed as normal, and then later on switched
back to active with only 92 tasks... it
I believe it shows only the tasks that have actually being executed, if
there were tasks with no data, they don't get reported.
I might be mistaken, if somebody has a good explanation, would also like to
hear.
On Fri, May 19, 2017 at 5:45 PM, Miles Crawford wrote:
> Hey ya'll,
>
> Trying to mig