On Tue, Nov 27, 2007 at 10:36:50PM +0100, Pierre Willenbrock wrote:
> Volker Grabsch schrieb:
> >
> > What about the "experimental" backend drivers?
> >
> > I'm especially interested in the new "genesys" backend. When
> > will it move from the "experimental" CVS to the "backend" CVS?
> > What doe
Pierre Willenbrock schrieb:
> Volker Grabsch schrieb:
>> On Fri, Nov 16, 2007 at 10:24:05AM -0500, m. allan noah wrote:
>>> This is the proposed timetable for the release of sane-backends 1.0.19:
>>>
>>> 2008-01-06 Feature freeze
>>> 2008-01-20 Code freeze
>>> 2008-02-03 Release
>> [...]
>>> If the
Volker Grabsch schrieb:
> On Fri, Nov 16, 2007 at 10:24:05AM -0500, m. allan noah wrote:
>> This is the proposed timetable for the release of sane-backends 1.0.19:
>>
>> 2008-01-06 Feature freeze
>> 2008-01-20 Code freeze
>> 2008-02-03 Release
> [...]
>> If there are any new backends that should be
Volker Grabsch wrote:
Hi,
> What about the "experimental" backend drivers?
>
> I'm especially interested in the new "genesys" backend. When
> will it move from the "experimental" CVS to the "backend" CVS?
> What does this move depend on? How can I help? Is there any
> site that shows the current
On Fri, Nov 16, 2007 at 10:24:05AM -0500, m. allan noah wrote:
> This is the proposed timetable for the release of sane-backends 1.0.19:
>
> 2008-01-06 Feature freeze
> 2008-01-20 Code freeze
> 2008-02-03 Release
[...]
> If there are any new backends that should be included in that release
> and h
On Nov 16, 2007 12:22 PM, wrote:
> > If there are any new backends that should be included in that release
> > and haven't been committed to CVS yet, please tell us NOW. We will
> > endeavour to help new backend authors get their code included.
>
>
> My hs2p backend for the Ricoh IS450/420 seems
On Friday 16 November 2007, m. allan noah wrote:
> This is the proposed timetable for the release of sane-backends 1.0.19:
>
> 2008-01-06 Feature freeze
> 2008-01-20 Code freeze
> 2008-02-03 Release
>
> The dates may move a few days if required. This is a longer
> 'pre-freeze' period than normal, b
This is the proposed timetable for the release of sane-backends 1.0.19:
2008-01-06 Feature freeze
2008-01-20 Code freeze
2008-02-03 Release
The dates may move a few days if required. This is a longer
'pre-freeze' period than normal, but it seems justified given the
longer development period and t