Glenn,
I've installed an 80+kW and a couple 10+kW systems using this Nuance
system. They are assembled fairly quickly and the legs are adjustable for
uneven ground, which is nice.
The ease of driving the cable anchors into the ground will, of course,
depend on the site. Luckily, i had no issue wi
Glen,
I just completed a three aray project. Call me @ 585-748-1870 and I'll tell
you all about it.
Christopher Schaefer
On Mon, Sep 9, 2019 at 3:31 PM Jerry Shafer
wrote:
> Wrenches/Glen
> I know nuance, they must be trailered or crained into position, leveled on
> site and cables are driven i
Wrenches/Glen
I know nuance, they must be trailered or crained into position, leveled on
site and cables are driven in and pre-loaded and cable locks installed. I
have there products around California along with the predecessor. Delivery
can be an issue and there team does the cables so that's some
Hello Wrenches,
We are looking at alternatives to pile driving and helical piles and
concrete piers for small residential ground mount systems.
I have just found Nuance Energy who makes a system that is basically set on
the grade, and with cables and pivoting duckbill earth anchors and attache