balance?
> How big are the inverters? Are they all the same size?
> Is it a 208 or 480 service?
>
> -Glenn
>
> From: RE-wrenches [mailto:re-wrenches-boun...@lists.re-wrenches.org] On
> Behalf Of Jay
> Sent: Wednesday, March 22, 2017 8:47 PM
> To: RE-wrenches
: Wednesday, March 22, 2017 8:47 PM
To: RE-wrenches
Subject: Re: [RE-wrenches] 2014 NEC 705-100 (A)
Hi Glenn
I had it correct in the subject, but got it wrong below, here is the correct
number
2014NEC, 705-100 (a)
On Mar 21, 2017, at 8:09 PM, Glenn Burt mailto:glenn.b...@glbcc.com
3/21/2017 21:34
> To: RE-wrenches
> Subject: [RE-wrenches] 2014 NEC 705-100 (A)
>
> HI All,
>
> I’ve got a client who’s having some issues with the building department. (for
> the 705-11-A NEC 2014)
> Now it is true that we in California are now in 2014 NEC)
> The
Of jay
Sent: Tuesday, March 21, 2017 6:35 PM
To: RE-wrenches
Subject: [RE-wrenches] 2014 NEC 705-100 (A)
HI All,
I’ve got a client who’s having some issues with the building department. (for
the 705-11-A NEC 2014) Now it is true that we in California are now in 2014
NEC) They are saying that
HI All,
I’ve got a client who’s having some issues with the building department. (for
the 705-11-A NEC 2014)
Now it is true that we in California are now in 2014 NEC)
They are saying that he isn’t allowed to install the 3rd inverter onto a 3
phase service
( this system was done in stages, usi