Re: [RE-wrenches] SMA connection box access

2019-12-03 Thread Jerry Shafer
Wrenches It has always been a "no no" to modify any inverter due to warranty concerns but with the -41 if there is an issue it's only the top half of the inverter now to swap so that's a plus but l would get it in writing first anyway to be safe Jerry On Tue, Dec 3, 2019, 6:05 PM frenergy wrote:

Re: [RE-wrenches] SMA connection box access

2019-12-03 Thread William Miller
Bill: Increasing KO size voids warranty. In the past, SMA might repair a dead modified inverter, if possible, but would not exchange one. The logistical difference is, you have to send your modified defective inverter in and wait instead of receiving a refurbished replacement promptly. Wm

[RE-wrenches] SMA connection box access

2019-12-03 Thread frenergy
Wrenchers,             This particular install requires 6 Gauge for the AC output from a few SB7.7..-41 inverters (for voltage drop). Pretty tight for the 3/4" knock-outs in that inverter.  Any harm in using a step-drill to open it up to a 1" KO?  Any experiences with this?  I'm trying to

Re: [RE-wrenches] Schneider support?

2019-12-03 Thread Dave Angelini Offgrid Solar
I would hope that you guys are feeding this back. I tell them what you are saying but better from you. I agree that Insight 2 is missing the most important screen that gateway and combox have and that is the battery summary screen. A 24 hour picture of the system that has months of data by the

Re: [RE-wrenches] Schneider support?

2019-12-03 Thread Howie Michaelson
Hi Glen, My experience with Schneider Support over the last several months has been very variable in terms of how accessible they are. There have been times when I ring right through, and others when I'm on hold for more than an hour (I think my personal record was a total of 2.5 hours in one day

Re: [RE-wrenches] NEC 2014 690.12 Rapid Shutdown - for multiple arrays

2019-12-03 Thread Lloyd Hoffstatter
Al, You may find this article and the one referenced to be helpful https://www.purepower.com/blog/nec-690-12-rapid-shutdown-length Best regards, Lloyd Hoffstatter Sunstruck Consulting Sent from Mail for Windows 10 From: Al Frishman

[RE-wrenches] NEC 2014 690.12 Rapid Shutdown - for multiple arrays

2019-12-03 Thread Al Frishman
Hey Wrenchers, What is your interpretaion regarding NEC 2014 690.12 Rapid Shutdown of PV Systems on Buildings when dealing with multiple arrays separated by 4 ft paths on flat roofs.For example can one inverter located at the East end of an array be connected to solar panels on both the adja