For some of our off grid customers we have installed the combiner on the
array right behind the gimble and then only run the home run wire down,
fewer wires is better. We try to keep the run in a loop 720` real close to
the gimble, the loop reduces wire stress and we have had no failures.
We used to just bundle the PV cables and secure them close to the pivot
point at both the rack and the pole with insulated wire loom clamps. We
always made a big enough loop to handle full articulation, but not too
long so they wouldn't catch on the Combiner box, etc. We also started
using b
Hi Wrenches,
I'm looking for advice on the best way(s) to secure PV source circuit
wiring on a dual axis tracker. I've never wired one up before and it seems
tricky. This particular tracker is 12 modules, 3 strings. Is it best to
run a flexible conduit up the pole and leave plenty of excess con
Wrenches,
Does anyone know whether a flashing state of "Bulk MPPT" on an Apollo T80
Charge controller means something other than the first stage of the absorb
cycle? This is on a DC coupled Net Metered system installed by another
company which is long since out of business. I've looked all throu