Wrenches,
We have a high-end client for whom we are installing a 12 kWp system on an
essentially flat roof. The terrain slopes down from the street to the house
(and there is an additional 2.5 deg slope on the roof in the same
direction), hence making the array visible at some point away from t
We are installing a PV system where an electrical contractor left us
an easy way to interface with the grid. The contractor does
extremely clean work which exceeds NEC requirements, and the local
code authorities are very happy with him.
What he left us was a 200 A, feed through breaker box t
So why does the list Xantrex rep not
reply to this inquiry?
Todd
jay peltz wrote:
Hi Todd,
I agree. I sure like what I've seen, but that is a large hole,
jay
peltz power
On Jul 24, 2008, at 10:07 PM, Todd Cory wrote:
I wish
they would address the question
Hi Todd,
I agree. I sure like what I've seen, but that is a large hole,
jay
peltz power
On Jul 24, 2008, at 10:07 PM, Todd Cory wrote:
I wish they would address the question I asked about why they
neglected to include an amp hour meter that communicates with their
charge controller on a b
If you ever tried to replace the ground fault fuse in the CC you would wonder
what they were thinking about while designing this error. (clearly not the
installer or service person) Yes I tried to bring this to there attention.
Also if they would consider the selection of breakers for there p