Our spreadsheet for Sprint 2 had some flaws. We weren't reporting our time
remaining each day consistently and the calculations in my spreadsheet were
slightly off.
We're going to try a new spreadsheet for this next sprint (starting Tuesday)
until we make the move to Greenhopper in a few weeks.
-
Hi,
On Fri, Aug 20, 2010 at 11:19 AM, Moriz Gupte wrote:
> May I venture to share these questions:
> Regarding the snowstorm sprint2 backlog: I have always tried to observe
> other teams using scrum and I have a question regarding negative daily
> velocity values. I am not familiar with this and
May I venture to share these questions:
Regarding the snowstorm sprint2 backlog: I have always tried to observe
other teams using scrum and I have a question regarding negative daily
velocity values. I am not familiar with this and am thinking if this is the
case, then it could mean that burndown g