[ACTIVITY]

2016-07-15 Thread Wookey
* Back from holidays catch-up * Jetson TK1 board ready to deploy in LAB, but investigating why debian 4.5 kernels work and 4.6 don't before handover. [BB-261/LAB-218] Wookey -- Principal hats: Linaro, Debian, Wookware, ARM http://wookware.org/ signature.asc Description: Digital signature ___

[ACTIVITY] week6+7 2016

2016-02-19 Thread Wookey
ILP32 Bootstrap [BB-277 20%] Started, reviewed names via cross-distro list Updated DPKG and configure patches. testing Fixup packages for arm64 [50%] Tried to get openvrml building on arm64 with dh-autoreconf. Bugs and patches updated Robot OS 10% [BB-163 leftovers] Advised on some issues wi

[ACTIVITY] week1-2

2016-01-15 Thread Wookey
~Getting Robot-OS packaged [BB-101 80%] More copyright review, package review and uploading All packages except the last one (ros-rviz) are now in Debian testing Status page: https://wiki.debian.org/DebianScience/Robotics/ROS/Packages Arm64 buildd maintenance [BB-86 20%] Installed new machine

[ACTIVITY] Week48

2015-11-20 Thread Wookey
Getting Robot-OS packaged [BB-101 100%] Lots of copyright review, package review and uploading Clarification sought from upstream Status page: https://wiki.debian.org/DebianScience/Robotics/ROS/Packages Updated Multiarch packaging docs on maintainer feedback Wookey -- Principal hats: Linaro,

[ACTIVITY] week46-47

2015-11-16 Thread Wookey
Debian-UK minidebconf - [20%] Improved cmake multiarch docs ROS work Getting Robot-OS packaged [BB-101 40%] Fix descriptions and File ITPs (36 so far) [BB-174] Analysis of CISST non-OSI licence [BB-174] Useful copyright file granularity discussion [BB-174] Upload packages Provide D01 presee

[ACTIVITY] Week44

2015-11-02 Thread Wookey
Getting Robot-OS packaged [BB-101 50%] Edit descriptions and review copyright for ros packages [BB-174] ompl progressed from NEW into archive Provide D01 preseed file [BB-208 30%] Get D01 PXE booting again NMU Debian arm64 packages [BB-86 20%] Built 'contrib' packages depending on pgplot5 N

[ACTIVITY] Week 42-43

2015-10-23 Thread Riku Voipio
== Progress == * RobotOS aarch64 work (BB-101 20%) * Qemu linux-user patches (10%) * builddeb: remove debian/files before build landed to 4.3-rc6 (5%) * kvmtool now in debian: https://tracker.debian.org/pkg/kvmtool (5%) * Debian/jessie armhf repo added (BB-188 10%) * repo.linaro.org updates and do

[ACTIVITY] Week 43

2015-10-23 Thread Wookey
Getting Robot-OS packaged [BB-101 85%] Review, fix and upload ompl (Open Motion Planning Library). Now in NEW. Collada-dom accepted into archive All ros packages renamed to ros-*. copyright review underway All 50 out of 51 packages built for arm64 in test bootstrap NMU Debian arm64 packages [

[ACTIVITY] Week 41 & 42

2015-10-16 Thread Wookey
Getting Robot-OS packaged [BB-101 15%] Investigate/specify subtasks Package collada-dom - Done [BB-153 70%] Find and discuss with Debian-Science/Debian-robotics people NMU Debian arm64 packages [BB-86 15%] Wookey -- Principal hats: Linaro, Debian, Wookware, ARM http://wookware.org/ signatu

[ACTIVITY] Week 40-41

2015-10-09 Thread Riku Voipio
== Progress == * Connect wrap up (20%) * OpeNNi2 for aarch64 (BB-155 20%) * RoboOS investigations (BB-101 20%) * Qemu linux-user update (10%) * Added PPA for Nicolas (BB-127 10%) * Resend patch for kernel builddeb regression (10%) * CI fixes (10%) == Plans == * RobotOS aarch64 work (BB-101 and sub

[ACTIVITY] Week 40

2015-10-02 Thread Koen Kooi
== Progress == * Connect wrap up in jira (20%) * ELC-E preparation (40%) * Release fixes (5%) * meta-96boards maintenance (5%) * OE builds (30%) == Plans == * ELC-E -- Koen Kooi Builds and Baselines | Release Manager Linaro.org | Open source software for ARM SoCs ___

[ACTIVITY] week37

2015-09-12 Thread Wookey
Write-up debconf multiarch/cross mini-sprint (BB-87 40%) NMU 3 arm64 build-failures (BB-86 25%) Packaging training talk @ARM 20% Wookey -- Principal hats: Linaro, Debian, Wookware, ARM http://wookware.org/ ___ linaro-dev mailing list linaro-dev@lists.l

[ACTIVITY] Week 37

2015-09-11 Thread Koen Kooi
== Progress == * meta-luv work (30%) * OE CI loops (10%) * Connect preparations (10%) * ELC-E preparation (10%) * Release preparations (30%) * meta-96boards maintenance (10%) == Plans == * vacation -- Koen Kooi Builds and Baselines | Release Manager Linaro.org | Open source software for ARM SoC

[ACTIVITY] Week 37

2015-09-11 Thread Riku Voipio
== Progress == * deb-pkg patch DONE now in 4.3 (BB-58 10%) * kvmtool debian and CI upstream review (BB-102 30%) - https://ftp-master.debian.org/new/kvmtool_0.20150908-1.html * Connect preparations (10%) * KVM and XEN jenkins-job-builder changes, 30% * other CI changes 20% == Plans == * invest

[ACTIVITY] Week 36

2015-09-04 Thread Riku Voipio
== Progress == * deb-pkg source package creation patch (BB-58 40%) * The v5 patch has been accepted upstream, but probably too late for 4.3 * kvmtool packaging (BB-102 30%) * Test packages at: http://repo.linaro.org/ubuntu/linaro-overlay/pool/main/k/kvmtool/ * ITP tracked at bigs.debian.org

[ACTIVITY] Week 36

2015-09-03 Thread Koen Kooi
== Progress == * Fix OE build issues (60%) * Prepare for SFO15 (10%) * Migrate OE CI jobs to linaro-cp (10%) * Sort out community patches and backports for meta-linaro (10%) * 15.08 release cleanup (10%) == Plans == * Adapt release scripts to s3 * Modernize OE CI jobs some more * Fix OE source mir

[ACTIVITY] Week 30

2015-08-10 Thread Koen Kooi
== Progress == * Address issues caused by the new layout for r.l.o (50%) * Reinstate gcc-linaro 4.9-2015.06 (5%) * Fix binutils-linaro issues in OE (5%) * Fix gdb-linaro issues in OE (5%) * Prepare for 15.08 release (15%) * Looked at OE CI jobs (20%) == Plans == * Document the new release scripts

[ACTIVITY] Week 30

2015-08-10 Thread Riku Voipio
== Progress == * Investigated name resolution issue in LAVA (BUG-1695 30%) * Created patch for resolved to read /proc/net/pnp to avoid the issue to begin with (10%) - https://github.com/systemd/systemd/pull/872 * Fixed KVM and Xen CI loops (30%) * Moved prebuilt image from EC2 to docker https://r

[ACTIVITY] Week 30

2015-07-27 Thread Andrey Konovalov
== Progress == * BB-29 "ENG: Linux linaro baseline maintenance" (80%): - added the updated Android topic back into linux-linaro-core-tracking tree, updated llct and ll to v4.2-rc3, tagged the 15.07 linux-linaro kernel release - fixed vexpress64 linux-linaro CI builds by removing the step

[ACTIVITY] Week 29

2015-07-17 Thread Koen Kooi
== Progress == * Deploy new layout for releases.l.o (10%) * Start meta-luv (60%) * Dragonboard support for meta-96boards (20%) * OE maintenance (10%) == Plans == * Find mind bleach to erase any recollection luv-yocto contents and quality. -- Koen Kooi Builds and Baselines | Release Manager Lina

[ACTIVITY] Week 28

2015-07-13 Thread Koen Kooi
== Progress == * Deploy new layout for releases.l.o * Integrated new linaro gcc into OE * Fixed OE build issues == Plans == * Start meta-luv -- Koen Kooi Builds and Baselines | Release Manager Linaro.org | Open source software for ARM SoCs ___ linaro-

[ACTIVITY] LAVA team weekly report, week 28

2015-07-06 Thread lava-team
Team Work Logged # milo Progress # * LAVA-1511 - Upstream Kernel CI * LAVA-1811 - Frontend UI improvements/requests (100.0%) * Completed javascript libraries refactoring. * Created a per-branch view of a job. View is a copy of the generic job one. * Switch

[ACTIVITY] Week 26

2015-06-26 Thread Koen Kooi
== Progress == * release == Plans == * Deploy new lay out * study LEAP -- Koen Kooi Builds and Baselines | Release Manager Linaro.org | Open source software for ARM SoCs ___ linaro-dev mailing list linaro-dev@lists.linaro.org https://lists.linaro.org

[ACTIVITY] Week 25,26

2015-06-26 Thread Riku Voipio
== Progress == * deb-pkg and perf updates (DEVPLAT-303 60%) - deb-pkg improvents at: https://github.com/suihkulokki/linux/commits/deb-pkg-4.1 - perf debian source package addition; https://github.com/suihkulokki/linux/commits/perf-pkg-4.1 * Finalized generic-package-builder deprecation in CI (D

[ACTIVITY] LAVA team weekly report, week 25

2015-06-16 Thread lava-team
Team Work Logged # tyler-baker Progress # * LAVA-1511 - Upstream Kernel CI * LAVA-2181 - Emergency fix for build trigger (23.08%) * Created and tested a patch on kbuilder01, to fix a syntax error introduced by a previous commit. (log #3h hours) * LAVA-1608 -

[ACTIVITY] Week 24

2015-06-16 Thread Koen Kooi
(Out sick for 3 days) == Progress == * OE maintenance (DEVPLAT-87) (20%) * ELC-E abstracts (20%) == Plans == * Releases layout * Submit ELC-E lightning talk * Arndale issues * meta-luv -- Koen Kooi Builds and Baselines | Release Manager Linaro.org | Open source software for ARM SoCs __

[ACTIVITY] Week 24

2015-06-12 Thread Riku Voipio
== Progress == * LKP Arm/Arm64 porting (DEVPLAT-377 40%) * KVM job vivid migration (30%) * v3 of deb-pkg source package (DEVPLAT-303 30%) == Plans == * Test and send to tianocore list fastboot sparse image support * Add perf/linux-tools package creating to builddeb * 1 day off, Midsummer eve (perh

[ACTIVITY] Week 24

2015-06-12 Thread Andrey Konovalov
== Progress == * June 12th was a day off: local holiday (20%) * CARD-788 "EPIC: Linux linaro baseline maintenance" (80%): - moved linux-linaro kernel tree to v4.1-rc7. - llct and ll CI jobs updated to use the rootfs with gator daemon version matching the kernel driver - old llct CI job is u

[ACTIVITY] Week 23

2015-06-08 Thread Andrey Konovalov
== Progress == * CARD-788 "EPIC: Linux linaro baseline maintenance" (100%): - moved linux-linaro kernel tree to v4.1-rc6. - old llct CI job is updated and its configuration is moved to ci/job/configs.git. The corresponding build trigger created. == Plans == * CARD-788 "EPIC: Linux linaro

[ACTIVITY] Week 23

2015-06-07 Thread Koen Kooi
== Progress == * luvOS (60%) * boost breackage (30%) * new releases layout (10%) == Plans == -- Koen Kooi Builds and Baselines | Release Manager Linaro.org | Open source software for ARM SoCs ___ linaro-dev mailing list linaro-dev@lists.linaro.org ht

[ACTIVITY] Week 23

2015-06-05 Thread Riku Voipio
== Progress == * LKP Arm/Arm64 support (DEVPLAT-377 40%) * LKP lava integration (DEVPLAT-377 50%) == Plans == * Test and send to tianocore fastboot sparse image support * Aarch64 support for remaining LKP benchmarks * Re-do perf make deb-pkg support so we can have up matching perf and debs in repo

[ACTIVITY] LAVA team weekly report, week 23

2015-06-01 Thread lava-team
Team Work Logged # Last week was a team Sprint # * The team met this week to do some focused cross-training for members that had not yet worked on the new dispacher. Later in the week we started looking into some of the failures observed in the production lab an

[ACTIVITY] Week22

2015-05-29 Thread Wookey
cross-binutils updated and uploaded [ DEVPLAT-220 20% ] cross-gcc updated, worked on standalone support [ DEVPLAT-220 30% ] ilp32 wiki page: https://wiki.linaro.org/Platform/arm64-ilp32 [ DEVPLAT=374 20% ] multiarch and arm64 NMUs [ DEVPLAT-221 10% ] 32/64 multiarch help. Wookey -- Principal ha

[ACTIVITY] Week 22

2015-05-29 Thread Koen Kooi
== Progress == 4 day week, so the amounts should add up to 80% instead of 100%. * 15.05 release (70%) * New layout for releases.linaro.org (DEVPLAT-366) (5%) * planned for 15.06 * OE (CARD-787) (5%) * empty gerrit queue * 96borads (1.25%) * Rebase to 4.1rc4 * Update atf/edk2 recipe == Pl

[ACTIVITY] Week 22

2015-05-29 Thread Vishal Bhoj
== Progress == * Android Release (40 %) * Dragonboard build (30%) * Hikey build (30%) == Plans == * CI build for member builds. ___ linaro-dev mailing list linaro-dev@lists.linaro.org https://lists.linaro.org/mailman/listinfo/linaro-dev

[ACTIVITY] Week 22

2015-05-29 Thread Riku Voipio
== Progress == * vivid updates (DEVPLAT-370 30%) - systemd job for Xen * Resubmit builddeb patches to linux-kbuild (DEVPLAT-303 30%) * Investigate LKP and initial Arm/Arm64 support (DEVPLAT-377 30%) - First patches accepted: https://git.kernel.org/cgit/linux/kernel/git/wfg/lkp-tests.git/commit/

[ACTIVITY] week 21 (ART optimizing compiler team)

2015-05-22 Thread Alexandre Rames
Here is a list of what people in the ART optimizing compiler team are working on: *Zheng Xu:* - Use LDP/STP on arm64 for slow paths (landed). https://android-review.googlesource.com/148028 - Speedup div/rem by constants on arm32 and arm64 (landed). https://android-review.googlesource.com/150710

[ACTIVITY] Week 21

2015-05-22 Thread Riku Voipio
== Progress == * vivid updates (DEVPLAT-370 70%) - docker images done - Xen job updated - upstart to to systemd conversions * generic-package-builder CI job 30% - template job didn't work as expected so back square one == Plans == * Remaining vivid update (KVM job at least) * Cleaner versi

[ACTIVITY] Week 20 & 21

2015-05-22 Thread Vishal Bhoj
== Progress == * Hikey board Android issues 50 % * R-LCR and M-LCR build setup 50 % == Plans == * Release * 410c build Regards, Vishal ___ linaro-dev mailing list linaro-dev@lists.linaro.org https://lists.linaro.org/mailman/listinfo/linaro-dev

[ACTIVITY] Week 21

2015-05-22 Thread Koen Kooi
== Progress == * New layout for releases.linaro.org (DEVPLAT-366) (60%) * received feedback from Fathi & Vishal * moved to 15.06 * OE (CARD-787) (35%) * fix gator license breakage * partially merge ODP patches * Fix binutils in 'dora' branch * 96borads (5%) * Rebase to 4.1rc3 * Update at

[ACTIVITY] LAVA team weekly report, week 21

2015-05-18 Thread lava-team
Team Work Logged # tyler-baker Progress # * LAVA-1511 - Upstream Kernel CI * LAVA-1524 - ARM KVM boot testing (3.33%) * Applied workaround for juno guest issue. * LAVA-1317 - lava-dispatcher maintenance * LAVA-2092 - Android Host Command Signals (6.67%) * R

[ACTIVITY] Week 20

2015-05-15 Thread Wookey
cross-gcc versioning for multiple uploads per native release [DEVPLAT-190 40%] (not actually working right yet) ilp32 investigations [DEVPLAT-374 40%] buildd multiarch-build support [DEVPLAT-190 10%] HD died in desktop - re-install time! Wookey -- Principal hats: Linaro, Debian, Wookware, ARM

[ACTIVITY] Week 20

2015-05-15 Thread Riku Voipio
== Progress == * repo.linaro.org setup for vivid etc (DEVPLAT-370 20%) * generic-package-builder CI job 50% * reviewing kvm issues in lava kernelci, 20% == Plans == * Cleaner version of sparse image support * Resubmit builddeb patches to linux-kbuild * Vivid docker images == Issues == * KVM ARM3

[ACTIVITY] LAVA team weekly report, week 20

2015-05-11 Thread lava-team
Team Work Logged # tyler-baker Progress # * LAVA-1429 - Dispatcher Refactoring * LAVA-1643 - 4. Trending Builds Boots and Tests (5.56%) * Added FVP base models for LSK testing. * LAVA-1317 - lava-dispatcher maintenance * LAVA-1981 - Basic integration of D02 (

[ACTIVITY] Week 19

2015-05-11 Thread Wookey
== Progress == * Added multilib support to cross-gcc packages [DEVPLAT-220] * Uploaded to test repo @ emdebian.org [DEVPLAT-220] * Enabled i386 cross-gcc builds (as well as amd64) [DEVPLAT-220] * Tested multiarch builds in the archive (needs wanna-build patches applying) [DEVPLAT-220] * Got 4.0 ke

[ACTIVITY] Week 19

2015-05-08 Thread Riku Voipio
== Progress == * CI jenkins-jobs-builders conversions (DEVPLAT-286 50%) * Dockerfile for creating vivid images (DEVPLAT-370 20%) * deb-pkg patch discussions (DEVPLAT-303 10%) * xen/mustang failure tests, 10% == Plans == * Cleaner version of sparse image support * Resubmit builddeb patches to linux

[ACTIVITY] Week 19

2015-05-08 Thread Koen Kooi
== Progress == * New layout for releases.linaro.org (DEVPLAT-366) (65%) * OE (CARD-787) (20%) * verify merge window patches * DEVPLAT-270 (toolchain) (10%) * Added URLtrigger to CI job * Unsuccesfully tried to get recent binary toolchains working * 96borads (5%) * Rebase to 4.1rc2 * Mer

[ACTIVITY] Week 18

2015-05-04 Thread Wookey
== Progress == * Tested debian 4.0~exp1 kernels on D01 with D-I: HD detection issue [40% CARD-1440] * Uploaded D-I, grub, kernel packages and binaries [10% CARD-1440] * Wiki page for Debian-installer on D01 [30% CARD-1440] * Cross-gcc updated for gcc-5. [10% DEVPLAT-220] * Created cross-gcc roadma

[ACTIVITY] LAVA team weekly report, week 19

2015-05-04 Thread lava-team
Team Work Logged # tyler-baker Progress # * LAVA-1429 - Dispatcher Refactoring * LAVA-1643 - 4. Trending Builds Boots and Tests (44.44%) * Publishing support added, and patch sent to Kevin for review/testing. Had to discuss with Milo a bit about the API param

[ACTIVITY] LAVA team weekly report, week 17

2015-04-26 Thread lava-team
Team Work Logged # tyler-baker Progress # * LAVA-1429 - Dispatcher Refactoring * LAVA-1643 - 4. Trending Builds Boots and Tests (40.0%) * Spent some timing reducing the duplication of the boot and test parsing. Branch is roughly based on the testing branch of

[ACTIVITY] Week 17

2015-04-24 Thread Riku Voipio
== Progress == * Tested UEFI on kvm/arm32 (DEVPLAT-360 30%) * Implemented sparse images for EDK2/Fastboot (69BOARDS-49 20%) - https://github.com/96boards/edk2/pull/11 * deb-pkg patch discussions (DEVPLAT-303 10%) * kvm/xen failure investigations, 20% == Plans == * KVM ARM32 booting with UEFI (D

[ACTIVITY] LAVA team weekly report, week 17

2015-04-20 Thread lava-team
Team Work Logged # tyler-baker Progress # * LAVA-1317 - lava-dispatcher maintenance * LAVA-1981 - Basic integration of D02 (21.43%) * Having issues with the networking interface in UEFI. Essentially it works about 1/3 of the time. Stakeholders respun me a new

[ACTIVITY] Week 16

2015-04-20 Thread Wookey
== Progress == * Tested and documented debian-installer on arm64 hardware (40% CARD-1722) * Confirmed jessie D-I + hilt-integration kernel installs to HD on D01 (50% DEVPLAT-257) * Uploaded cross-gcc-14 for jessie (RC bug) (10% DEVPLAT-220) == Plans == * Test cross-gcc in experimental * Build g

[ACTIVITY] Week 16

2015-04-20 Thread Vishal Bhoj
== Progress == * Spreadtrum CI loop for tshark (40 %) * Android 5.1 update on nexus 10 (10 %) * Project ARA (50 %) == Plans == * Project ARA * CI loop for ZTE member build. Regards, Vishal ___ linaro-dev mailing list linaro-dev@lists.linaro.org htt

[ACTIVITY] Week 16

2015-04-17 Thread Riku Voipio
== Progress == * CI bugfixes (lci-build-tools, linaro-cp usage in xen-packages etc) 30% * update UEFI and run perf test on hikey, found some aarch64 bugs in testcases: https://www.mail-archive.com/linux-kernel%40vger.kernel.org/msg868497.html (DEVPLAT-303 30%) * cleaned up debarch patch as requeste

[ACTIVITY] Week 16

2015-04-17 Thread Koen Kooi
== Progress == * OE (CARD-787) (20%) * fix strace build * DEVPLAT-319 (buildhistory) (25%) * DEVPLAT-270 (toolchain) (45%) * Added URLtrigger to CI job * Unsuccesfully tried to get recent binary toolchains working * 96borads (10%) * Rebase to post 4.0 * Update meta-96boards layer == Pla

[ACTIVITY] Week 15

2015-04-13 Thread Vishal Bhoj
== Progress == * Setup 5.0.1 Spreadtrum member build (35 %) * Setup optimus a80 member build (35%) * Project ARA ( 30%) == Plans == * Project ARA * Debug LAVA job failure for a80 build. Regards, Vishal ___ linaro-dev mailing list linaro-dev@lists.l

[ACTIVITY] Week 15

2015-04-11 Thread Andrey Konovalov
== Progress == * DEVPLAT-321 "clean up ILP32 build job" (0%): - closed. * CARD-788 "EPIC: Linux linaro baseline maintenance" (50%): - moved llct v4.0-rc7. A few issues in llct due to the android topic update to the aosp/android-3.18 resolved, but the others are arising. The last issue is

[ACTIVITY] Week 14

2015-04-11 Thread Andrey Konovalov
== Progress == * DEVPLAT-321 "clean up ILP32 build job" (35%): - with Fathi's help the linux-linaro-tracking-ll-ilp32.yaml has been fixed and added ci/job/configs.git. The jenkins job using this config is enabled. * CARD-788 "EPIC: Linux linaro baseline maintenance" (50%): - moved llct an

[ACTIVITY] LAVA team weekly report, week 15

2015-04-11 Thread lava-team
Team Work Logged # tyler-baker Progress # * LAVA-1317 - lava-dispatcher maintenance * LAVA-1981 - Basic integration of member board (26.67%) * After getting the memory issues sorted, I was able to flash the latest firmware provided in binary form from: https

[ACTIVITY] LAVA team weekly report, week 14

2015-04-03 Thread lava-team
Team Work Logged # tyler-baker Progress # * LAVA-1429 - Dispatcher Refactoring * LAVA-1643 - 4. Trending Builds Boots and Tests (32.0%) * Moved most kernelci.org projects to github. Merged testing branch to master, and retested functionality. Added cpufreq st

[ACTIVITY] LAVA team weekly report, week 14

2015-03-30 Thread lava-team
Team Work Logged # milo Progress # * LAVA-1429 - Dispatcher Refactoring * LAVA-1932 - dispatcher-slave: retry the HELLO (56.82%) * More code cleanup and pushed for review first attempt for the HELLO message retry logic. * Continued working on HELLO-retry lo

[ACTIVITY] Week 13

2015-03-30 Thread Vishal Bhoj
== Progress == * Android Release (10%) * Gerrit triggers for Android jobs (80%) * Project ARA (10%) * Hikey Android update and Mali Integration (20%) == Plans == * Project ARA * Hikey Mali integration * Docker plugin integration Regards, Vishal _

[ACTIVITY] Week 13

2015-03-30 Thread Andrey Konovalov
== Progress == * mourning leave (60%) * DEVPLAT-321 "clean up ILP32 build job" (15%): - updated the current ILP32 build job to use the standard QA's LTP test case (it has got the 2 required fixes), and to pick up the latest ILP32 and LP64 rootfs'es (vs the hardcoded ones). Submitted for

[ACTIVITY] Week 13

2015-03-30 Thread Dileep Katta
== Progress == * CARD 1103: upstream u-boot fastboot (CARD-1103: 100 %) - Followed up on DRA7 patches, sent updates - 4 patches were reviewed == Plans == * upstream u-boot fastboot (CARD-1103: 100 %) - Need to verify flash zImage functionality -

[ACTIVITY] Week 13

2015-03-28 Thread Wookey
Solved BIOS update issues on D01 (thanks luca) [CARD-1440] 60% Built,uploaded,unblocked cross-binutils 2.25-5 for jessie [DEVPAT-190] 20% Full debian rebuild in <48hrs on 14 moonshot nodes Wookey -- Principal hats: Linaro, Debian, Wookware, ARM http://wookware.org/ _

[ACTIVITY] Week 13

2015-03-27 Thread Riku Voipio
== Progress == * Boot KVM using UEFI (DEVPLAT-338 40%) * building perf as part of make deb-pkg (DEVPLAT-303 30%) * Fix Xen jobs to use always latest Xen binary 20% == Plans == * building perf as part of make deb-pkg DEVPLAT-303 * Keep moving Xen/KVM jobs over to configs.git for CI 2.0 == Issues

[Activity] Week 12

2015-03-23 Thread Dileep Katta
== Progress == * CARD 1103: upstream u-boot fastboot (CARD-1103: 100 %) - Changed DRA7 patches as per the comments, v3 patches are in internal review. - Working on verifying on DRA7 == Plans == * upstream u-boot fastboot (CARD-1103: 100 %) - Test on DRA7 boa

[ACTIVITY] LAVA team weekly report, week 13

2015-03-23 Thread lava-team
Team Work Logged # tyler-baker Progress # * LAVA-1317 - lava-dispatcher maintenance * LAVA-1926 - lava-bot ci (20.0%) * lava-bot is back in service. Currently we it is watching lava-coordinator, lava-server, and lava-dispatcher on all development branches. +1

[ACTIVITY] Week 12

2015-03-23 Thread Riku Voipio
== Progress == * Testing Arm32 guests on Arm64 for KVM (DEVPLAT-322 10%) * Converted KVM guest images to GPT and moved to configs.git (20%) * Boot KVM using UEFI (DEVPLAT-338 50%) - almost done, still need to move to QA repo from personal, https://git.linaro.org/people/riku.voipio/test-definition

[ACTIVITY] Week 12

2015-03-21 Thread Koen Kooi
== Progress == * OE (CARD-787) (60%) * debug grub gcc ICE with TCWG - FIXED (https://bugs.linaro.org/show_bug.cgi?id=1254) * DEVPLAT-332 (uefi) (5%) * Address gcc 4.9 issues * Deploy all the .bin files, not just fip.bin * DEVPLAT-270 (toolchain) (30%) * Get bitten by layout change, again

[ACTIVITY] Week 12

2015-03-20 Thread Wookey
== Progress == * Provided support for mass-debian rebuild work at ARM (20%) * Built/tested/uploaded amd64 and i386 cross-gcc versions for jessie (10%) * Updated cross-gcc for more front-ends (10%) * Fought D01 board bootloader about FTP/TFTP boot updates (70%) == Plans == * Test debian-installer

[ACTIVITY] Week 12

2015-03-20 Thread Vishal Bhoj
== Progress == * Android jobs to work with gerrit triggers (80%) * Project Ara (10%) * Android Release (10%) == Plans == * Android Release * Project Ara Regards, Vishal ___ linaro-dev mailing list linaro-dev@lists.linaro.org http://lists.linaro.org/m

[Activity] Week 11

2015-03-16 Thread Dileep Katta
== Progress == * CARD 1103: upstream u-boot fastboot (CARD-1103: 100 %) - Worked on USB Initialization and changed fastboot to accept usb controller index as an argument, Submitted the patch - Worked with TI for getvar patches, 4 related patches are closed as no change re

[ACTIVITY] LAVA team weekly report, week 10

2015-03-16 Thread lava-team
Team Work Logged # tyler-baker Progress # * LAVA-1429 - Dispatcher Refactoring * LAVA-1643 - 4. Trending Builds Boots and Tests (16.0%) * Improvements to lava-ci were pushed. New platforms supported: * minnowboard-max * armada-370-mirabox Added retry l

[ACTIVITY] Week 10 & 11

2015-03-15 Thread Vishal Bhoj
== Progress == * Android 5.1 update (DEVPLAT-336, 20%) * Project ARA ( 60%) * Integrate docker slave to android-build (DEVPLAT-273-20%) == Plans == * Project Ara * Android jobs to work with gerrit triggers Regards, Vishal ___ linaro-dev mailing list l

[ACTIVITY] Week 11

2015-03-13 Thread Wookey
== Progress == * Investigated debian mass-rebuild methods * Specified debian full-rebuild system for ARM (65%) * Updated jessie cross-gcc versions for jessie (as gcc and binutils migrated) (15%) * Migrated amd64 packages unstable-> emdebian jessie repo * Investigated failed jessie buildd upgrade

[ACTIVITY] Week 11

2015-03-13 Thread Riku Voipio
== Progress == * Desting Arm32 guests on Arm64 for kvm (DEVPLAT-322 60%) - https://wiki.linaro.org/Core/Virtualization/HowTo/Arm32GuestOnAarch64 * Testing Uefi/KVM on 96boards (30%) == Plans == * Move linux-xen to configs.git (DEVPLAT-329) * Other CI 2.0 related tasks __

[ACTIVITY] Week 11

2015-03-13 Thread Koen Kooi
== Progress == * OE (CARD-787) (10%) * debug grub gcc ICE with TCWG ( https://bugs.linaro.org/show_bug.cgi?id=1254) * Add full wget to LAMP image (https://bugs.linaro.org/show_bug.cgi?id=1288 ) * DEVPLAT-265 (meta-aarch64) (60%) * Delete obsolete bbappends * Try to upstream changes (again)

[Activity 10] Week 10

2015-03-09 Thread Dileep Katta
== Progress == * CARD 1103: upstream u-boot fastboot (CARD-1103: 100 %) - Submitted DRA7 changes - Worked on the changes suggested by community on DRA7 - Looking into zImage, SPI and other environment variables == Plans == * upstream u-boot fastboot (CARD-110

[ACTIVITY] LAVA team weekly report, week 10

2015-03-06 Thread lava-team
Team Work Logged # tyler-baker Progress # * LAVA-1429 - Dispatcher Refactoring * LAVA-1643 - 4. Trending Builds Boots and Tests (16.0%) * Improvements to lava-ci were pushed. New platforms supported: * minnowboard-max * armada-370-mirabox Added retry l

[ACTIVITY] Week 10

2015-03-06 Thread Riku Voipio
== Progress == * Worked around Lava/Xen serial brokenness (40%) * Building Xen binary cleaned and moved to configs.git (DEVPLAT-329 20%) * Testing Uefi/KVM on 96boards (30%) * Help on Aarch64 optimizing (DEVPLAT-277 10%) == Plans == * Help on Aarch64 optimizing DEVPLAT-277 * Move linux-xen to conf

[ACTIVITY] Week 10

2015-03-06 Thread Koen Kooi
== Progress == * Release 15.02 (DEVPLAT-312) (1%) * OE (CARD-787) (93%) * Fix mozjs build for aarch64 * debug grub gcc ICE with TCWG * 96borads (5%) * Rebase to 4.0rc2 * Update meta-96boards layer * Discuss kernel tree == Plans == ___ linaro-dev

[Activity] Week 9

2015-03-03 Thread Dileep Katta
== Progress == * CARD 1103: upstream u-boot fastboot (CARD-1103: 100 %) - Enabling fastboot for DRA7 - reboot-bootloader command is implemented for DRA7 as per latest submissions - Working with Angela for DRA7 specific environment variable implementation

[ACTIVITY] Week 9

2015-03-02 Thread Andrey Konovalov
== Progress == * CARD-788 "EPIC: Linux linaro baseline maintenance" (5%): - linux-linaro schedule for 15.03 published on the wiki - tried moving llct to v4.0-rc1: 15 conflicts when merging the android topic. They seem to be not hard to resolve though. * CARD-1161 "Add ILP32 support for ARM

[ACTIVITY] LAVA team weekly report, week 10

2015-03-02 Thread lava-team
Team Work Logged # tyler-baker Progress # * LAVA-1429 - Dispatcher Refactoring * LAVA-1643 - 4. Trending Builds Boots and Tests (5.88%) * Added support in the build scripts for changing out the toolchain. Create prototype script to provide TCWG build/boot tes

[ACTIVITY] Week 9

2015-03-02 Thread Riku Voipio
== Progress == * Investigated Lava/Xen serial brokenness (BUG-1245 40%) * Help on Aarch64 optimizing (DEVPLAT-277 40%) == Plans == * Investigate or give up on Lava/Xen brokenness * Help on Aarch64 optimizing DEVPLAT-277 * Arm32 guests on Arm64 for kvm DEVPLAT-322 == Issues == * Serial characters

[ACTIVITY] Week 9

2015-03-01 Thread Vishal Bhoj
== Progress == * Integrate docker slave to android-build (DEVPLAT-273-40%) * Project ARA (60%) == Plans == * Integrate docker slave to android-build * Project ARA Regards, Vishal ___ linaro-dev mailing list linaro-dev@lists.linaro.org http://lists.l

[ACTIVITY] Week 9

2015-03-01 Thread Trevor Woerner
== Progress == DEVPLAT-271 luvOS CI loop - pushed first draft of luvOS.yaml DEVPLAT-289 CI bringup: A80 Optimus board - coordinated with LHG (Will and Zhenhua) to get an image to the LAVA team - my download of the 53GB of sources has finally completed (it takes about a week for me to pull that muc

[ACTIVITY] Week 9

2015-02-27 Thread Koen Kooi
== Progress == * Release 15.02 (DEVPLAT-312) (90%) * OE (CARD-787) (30%) * Fix RC builds * 96borads (10%) * Boot 4.0rc * Update meta-96boards layer == Plans == Fix issues before the weekend starts. ___ linaro-dev mailing list linaro-dev@lists.lina

[ACTIVITY] Week 8

2015-02-24 Thread Dileep Katta
== Progress == * CARD 1103: upstream u-boot fastboot (CARD-1103: 100 %) - Followed upon the submitted patches, handled review comments - Erase command and other fixes got accepted - Worked on DRA7 specific changes == Plans == * upstream u-boot fastboot (CARD-1

[ACTIVITY] Week 8

2015-02-23 Thread Riku Voipio
== Progress == * Repaired docker cross-builds (20%) * Converted Xen to use proper packages (30%) * Finishing touches to ARMv8 native builders (now used for armhf too) (CARD-1729 20%) * Workaround race between archiving artifacts and post-build-repo (20%) == Plans == * Investigate BUG-1245 (Lava/X

[ACTIVITY] Week 8

2015-02-22 Thread Vishal Bhoj
== Progress == * CI bring up for TI member build (CARD-1216, 70%) * WiFi integration in Hikey Android build (CARD-1777, 30%) == Plans == * Android Release ___ linaro-dev mailing list linaro-dev@lists.linaro.org http://lists.linaro.org/mailman/listinfo/l

[ACTIVITY] LAVA team weekly report, week 8

2015-02-20 Thread lava-team
Team Work Logged # milo Progress # * LAVA-1511 - Upstream Kernel CI * LAVA-1811 - Frontend UI improvements/requests (98.42%) * Added unique values count for boot reports as we have on the email report. * Changed Google Analytics snippet to use the Universal

[ACTIVITY] Week 8

2015-02-20 Thread Koen Kooi
== Progress == * OE (CARD-787) * work around linux-dummy problems * fix perf build * work around openvswitch issues * drop snort from lng build * Triggered ILP32 build * 96borads * Fixed MMC bus-width on hikey * integrated UIM patches into BSP == Plans == * Convert more CI jobs to yaml *

[ACTIVITY] Week 7

2015-02-16 Thread Dileep Katta
== Progress == * CARD 1103: upstream u-boot fastboot (CARD-1103: 50 %) - submitted erase command - submitted 3 more patches with some bug fixes * Connect HKG 15 (50%) == Plans == * upstream u-boot fastboot (CARD-1103: 100 %) - submit other patches having comm

ACTIVITY] Week 6

2015-02-09 Thread Dileep Katta
== Progress == * CARD 1103: upstream u-boot fastboot (CARD-1103: 50 %) - Worked on fastboot patches - Done with fastboot erase command * FOSDEM, connect travel (50%) == Plans == * upstream u-boot fastboot (CARD-1103: 40 %) - work on other patches to be sent t

[ACTIVITY] Week 6

2015-02-06 Thread Vishal Bhoj
== Progress == * Integrated BT on member h/w on Android with 3.10 LSK (CARD-1778 100%) == Plans == * Connect ___ linaro-dev mailing list linaro-dev@lists.linaro.org http://lists.linaro.org/mailman/listinfo/linaro-dev

[ACTIVITY] Week 6

2015-02-06 Thread Riku Voipio
== Progress == * ARMv8 native builders for jenkins ready (CARD-1729 60%) * Juno enabled in KVM testing (20%) * Fixes and improvements to packages building CI for native builders etc (20%) == Plans == * Connect ___ linaro-dev mailing list linaro-dev@list

[ACTIVITY] LAVA team weekly report, week 6

2015-02-02 Thread lava-team
Team Work Logged # tyler-baker Progress # * LAVA-1511 - Upstream Kernel CI * LAVA-1830 - Implement file upload API in lava-ci (80.0%) * Had a quick discussion with Milo, who pointed out the example was incorrect. After fixing up the code, the single file uplo