That worked perfect!
Thanks for the help,
Dustin
On Sat, Oct 9, 2010 at 6:16 PM, Bernt Hansen wrote:
> Dustin Hoffman writes:
>
>> I have scheduled reminders for things that occur weekly over a period
>> of months. The problem is, that each of these scheduled items ap
I have scheduled reminders for things that occur weekly over a period
of months. The problem is, that each of these scheduled items appears
under the current day in the agenda view and the multiplier (eg 6x,
5x) keeps going up.
What I want is each of these scheduled items to appear only on the
da
I would like to export an estimate in column view via the text exporter.
When I export the file now, none of the hour estimates or summation of
estimates is displayed.
Thanks,
Dustin
___
Emacs-orgmode mailing list
Please use `Reply All' to send replies