From: Rohit Yadav
Sent: February 20, 2025 11:00 PM
To: dev@cloudstack.apache.org ;
us...@cloudstack.apache.org
Subject: Re: Timeline for the release of 4.20.1
Thanks for sharing the timeline Pearl, LGTM. It would be great if 4.20.1 is
released by late March or even early April to give us enough
To: dev@cloudstack.apache.org ;
us...@cloudstack.apache.org
Subject: Timeline for the release of 4.20.1
Hi All,
I propose the following timeline for the 4.20.1 release, which is targeted
for the end of Q1 2025.
- (5-6 weeks) Ongoing - Mid March 2025: Accept all bugs, issues,
improvements
Hi All,
I propose the following timeline for the 4.20.1 release, which is targeted
for the end of Q1 2025.
- (5-6 weeks) Ongoing - Mid March 2025: Accept all bugs, issues,
improvements allowed in LTS [1], i.e., code freeze by the end of the 2nd
week of March
- 1 week - To stabilize the 4.20.1 bra