Re: 4.5.0 status

2014-12-05 Thread Pierre-Luc Dion
RN just started, here are regular questions: 1. Do we need a new set of systemvmtemplate? 2. Any special consideration with 4.5? 3. Does new features from this filter is valid for the RN? https://issues.apache.org/jira/browse/CLOUDSTACK-7739?filter=12329800 4. Does it really contain 188 fixed from

Re: 4.5.0 status

2014-12-05 Thread Mike Tutkowski
That sounds really good. I can run my tests on RC0 then. If the vote for that one doesn't pass, I'm always free then for subsequent RCs to view what's been checked in since RC0 and determine if I think any of my tests should be re-run on the new RC. Thanks On Fri, Dec 5, 2014 at 6:58 PM, David N

Re: 4.5.0 status

2014-12-05 Thread David Nalley
So my plan is to let the first RC sit for a few days before calling for a vote. Hopefully an RC being around for testing will be enough for folks to actually go do some testing. We'll see how that works out. --David On Fri, Dec 5, 2014 at 5:58 PM, Mike Tutkowski wrote: > Yeah, I'd love to wait

Re: 4.5.0 status

2014-12-05 Thread Mike Tutkowski
Yeah, I'd love to wait for a formal RC before re-running automated and manual tests, but sometimes 3 days isn't really long enough. On Fri, Dec 5, 2014 at 2:01 PM, Sebastien Goasguen wrote: > > On Dec 5, 2014, at 3:58 PM, David Nalley wrote: > > > All of the test results I am aware of are on je

Re: 4.5.0 status

2014-12-05 Thread Sebastien Goasguen
On Dec 5, 2014, at 3:58 PM, David Nalley wrote: > All of the test results I am aware of are on jenkins.buildacloud.org > Generally, people don't start testing until we get RCs ready - hence > me trying to push out an RC. I want folks to start testing upgrade > paths, etc. it's one way to go, as

Re: 4.5.0 status

2014-12-05 Thread David Nalley
All of the test results I am aware of are on jenkins.buildacloud.org Generally, people don't start testing until we get RCs ready - hence me trying to push out an RC. I want folks to start testing upgrade paths, etc. I fully suspect we'll find issues with this first attempt. On Fri, Dec 5, 2014 a

Re: 4.5.0 status

2014-12-05 Thread Mike Tutkowski
Yeah, now that we're getting really close on 4.5, I'd like to rerun my regression tests early next week. They're not all automated yet so it generally takes me 2 to 3 days. On Friday, December 5, 2014, Sebastien Goasguen wrote: > Did we report test results, upgrade paths. > Are release notes re

Re: 4.5.0 status

2014-12-05 Thread Sebastien Goasguen
Did we report test results, upgrade paths. Are release notes ready ? -Sebastien > On 5 Dec 2014, at 05:16, David Nalley wrote: > > So we have no blockers currently logged, and are down to 15 critical > bugs. I am going to try and roll a 4.5.0 release candidate in the next > day or so. > > >

RE: 4.5.0 status

2014-12-04 Thread Animesh Chaturvedi
Message- > From: David Nalley [mailto:da...@gnsa.us] > Sent: Thursday, December 04, 2014 8:17 PM > To: dev@cloudstack.apache.org > Subject: 4.5.0 status > > So we have no blockers currently logged, and are down to 15 critical bugs. I > am > going to try and roll a 4.5.0 r

4.5.0 status

2014-12-04 Thread David Nalley
So we have no blockers currently logged, and are down to 15 critical bugs. I am going to try and roll a 4.5.0 release candidate in the next day or so. --David

Re: 4.5.0 - status - looming dates

2014-09-18 Thread Daan Hoogland
On Fri, Sep 19, 2014 at 5:29 AM, David Nalley wrote ​ a lot of tl;dr​ ​ and then​ : > This likely > means that we'll need a small army of quality fascists who take a > serious interest in quality, and are liberal with vetoes and reverts > until we get something that automates gating on quality. >

Re: 4.5.0 - status - looming dates

2014-09-18 Thread David Nalley
On Thu, Sep 18, 2014 at 6:19 AM, Sebastien Goasguen wrote: > > On Sep 18, 2014, at 5:08 AM, Daan Hoogland wrote: > >> David, >> >> What do you plan to do after branching in terms of merge-back and or >> cherry-picking. We are discussing here (Schuberg-Philis + Rohit + Ian + >> Wido (+ Sebastien))

Re: 4.5.0 - status - looming dates

2014-09-18 Thread Wido den Hollander
On 09/18/2014 11:08 AM, Daan Hoogland wrote: > David, > > What do you plan to do after branching in terms of merge-back and or > cherry-picking. We are discussing here (Schuberg-Philis + Rohit + Ian + > Wido (+ Sebastien)) that we would like to branch after getting master > stable and then when

Re: 4.5.0 - status - looming dates

2014-09-18 Thread Sebastien Goasguen
On Sep 18, 2014, at 5:08 AM, Daan Hoogland wrote: > David, > > What do you plan to do after branching in terms of merge-back and or > cherry-picking. We are discussing here (Schuberg-Philis + Rohit + Ian + > Wido (+ Sebastien)) that we would like to branch after getting master > stable and then

Re: 4.5.0 - status - looming dates

2014-09-18 Thread Daan Hoogland
David, What do you plan to do after branching in terms of merge-back and or cherry-picking. We are discussing here (Schuberg-Philis + Rohit + Ian + Wido (+ Sebastien)) that we would like to branch after getting master stable and then when the real release work is underway branching of 4.5. All new

4.5.0 - status - looming dates

2014-09-17 Thread David Nalley
Hi folks, 4.3.1 is out the door now, so I am trying to get things lined up around 4.5.0. Please consider us in feature freeze right now - and my plan is to branch 4.5.0 this coming weekend. I'd like to see us hit code freeze by end of October. Right now, we have 4 blocker bugs and 63 critical bu