Re: Planning for final lenny point release (5.0.10)

2012-02-28 Thread Adam D. Barratt
On 14.02.2012 21:36, Adam D. Barratt wrote: On Mon, 2011-12-12 at 23:05 +, Adam D. Barratt wrote: As the security team have recently confirmed that security support for lenny will end on February 6th (a year after the release of squeeze) it makes sense to schedule 5.0.10 to be after that d

Re: Planning for final lenny point release (5.0.10)

2012-02-26 Thread Daniel Baumann
On 02/25/2012 10:40 AM, Adam D. Barratt wrote: > Daniel? We really need to get dates sorted... sorry for the late answer, haven't been much arround the last days; anyhow, any date is fine. -- Address:Daniel Baumann, Donnerbuehlweg 3, CH-3012 Bern Email: daniel.baum...@progress-

Re: Planning for final lenny point release (5.0.10)

2012-02-25 Thread Adam D. Barratt
On Mon, 2012-02-20 at 21:11 +, Adam D. Barratt wrote: > On Tue, 2012-02-14 at 21:36 +, Adam D. Barratt wrote: > > 3-4/3 - Cambridge BSP. Should be do-able as long as I can get decent > > connectivity at the right time. :-) > > > > 10-11/3 - Joerg mentioned he's not available on the Sunday

Re: Planning for final lenny point release (5.0.10)

2012-02-21 Thread Adam D. Barratt
On Tue, 2012-02-21 at 10:20 +0100, Francesca Ciceri wrote: > On Mon, Feb 20, 2012 at 09:11:46PM +, Adam D. Barratt wrote: > > > On Tue, 2012-02-14 at 21:36 +, Adam D. Barratt wrote: > > > > 25-26/2 - Steve's not available for CDs > > > > > > > > 3-4/3 - Cambridge BSP. Should be do-able as

Re: Planning for final lenny point release (5.0.10)

2012-02-21 Thread Neil McGovern
I'm not free on the 25th, 3rd (daytime) and 10th/11th will be sporadic. Others in press may be available :) Neil (Press hat) On Mon, Feb 20, 2012 at 09:11:46PM +, Adam D. Barratt wrote: > On Tue, 2012-02-14 at 21:36 +, Adam D. Barratt wrote: > > 25-26/2 - Steve's not available for CDs >

Re: Planning for final lenny point release (5.0.10)

2012-02-21 Thread Francesca Ciceri
Hi, [quotation re-ordered] On Mon, Feb 20, 2012 at 09:11:46PM +, Adam D. Barratt wrote: > > On Tue, 2012-02-14 at 21:36 +, Adam D. Barratt wrote: > > > 25-26/2 - Steve's not available for CDs > > > > > > 3-4/3 - Cambridge BSP. Should be do-able as long as I can get decent > > > connecti

Re: Planning for final lenny point release (5.0.10)

2012-02-20 Thread Adam D. Barratt
On Tue, 2012-02-14 at 21:36 +, Adam D. Barratt wrote: > 25-26/2 - Steve's not available for CDs > > 3-4/3 - Cambridge BSP. Should be do-able as long as I can get decent > connectivity at the right time. :-) > > 10-11/3 - Joerg mentioned he's not available on the Sunday, but that's > only rea

Re: Planning for final lenny point release (5.0.10)

2012-02-16 Thread Philipp Kern
On Tue, Feb 14, 2012 at 09:36:38PM +, Adam D. Barratt wrote: > 25-26/2 - Steve's not available for CDs > > 3-4/3 - Cambridge BSP. Should be do-able as long as I can get decent > connectivity at the right time. :-) > > 10-11/3 - Joerg mentioned he's not available on the Sunday, but that's > o

Re: Planning for final lenny point release (5.0.10)

2012-02-15 Thread Goswin von Brederlow
"Adam D. Barratt" writes: > On Mon, 2011-12-12 at 23:05 +, Adam D. Barratt wrote: >> Working on the four-monthly schedule for oldstable, the next lenny point >> release would be due in early February. >> >> As the security team have recently confirmed that security support for >> lenny will

Re: Planning for final lenny point release (5.0.10)

2012-02-14 Thread Adam D. Barratt
On Mon, 2011-12-12 at 23:05 +, Adam D. Barratt wrote: > Working on the four-monthly schedule for oldstable, the next lenny point > release would be due in early February. > > As the security team have recently confirmed that security support for > lenny will end on February 6th (a year after t