All,
The weekly report for the Linaro Infrastructure team may be found at:-
Status report: https://wiki.linaro.org/Platform/Infrastructure/Status/2010-12-23
Burndown chart: This link is awaiting the production of new burndown charts.
The Infrastructure related blueprints from the maverick cycle, of which
currently there are 4 active ones (4 from the last report), are showing that
there are 9 work items in progress (8 last report), and 10 work items to
undertake (11 last report). These are to be moved into the natty cycle if still
required.
* arm-m-validation-dashboard; 0 work items completed (1 last report); 4 in
progress (3 last report); 6 to do (6 last report); 0 work item added (1 last
report)
* arm-m-image-building-console; no change in status from last report; 3 in
progress; 3 to do
* arm-m-automated-testing-framework; no change in status from last report; 1 in
progress; 0 to do
* arm-m-testsuites-and-profilers; no change in status from last report; 1 in
progress; 1 to do
In the natty cycle, the following lists the current active Blueprints, or
Blueprints planned and not started. Currently there are 5 active Blueprints (4
from the last report), which are showing that there are 9 work items in
progress (8 last report), 43 work items to undertake (41 last report), 2 work
items postponed in total (2 last report) and 0 work items added (1 item added
last report).
* other-linaro-n-improve-linaro-media-create: 8 work items completed in total
(7 last week); 2 work items in progress (3 last week); 8 work items to do (8
last week); 1 work item added this week (1 last week).
* other-linaro-n-test-result-display-in-launch-control: 0 work items
completed (0 last week); 1 work item in progress (1 last week); 10 work items
to do (10 last week); 0 work items added (0 last week)
* other-linaro-n-patch-tracking: 0 work item completed (0 last week); 2 work
items in progress (2 last week); 9 work items to do (9 last week)
* other-linaro-n-image-building: 2 work items in progress (2 last week); 5
work items to do (5 last week); 2 work items postponed (2 last week); 0 work
items added (0 last week)
* other-linaro-n-continuous-integration: Not started - awaiting a Hudson build
server (RT#42278).
* other-linaro-n-package-development-tools: Not Started; 9 work items to do
* other-linaro-n-benchmark-reports-in-launch-control: 2 work item completed (2
last week); 2 work items in progress (2 last week); 2 work items to do (2 last
week)
Specifics accomplished this week include:-
* Reports have indicated reduced accomplishments due to people being on leave.
* Work on a comprehensive MX51 test plan than headless one:
https://wiki.linaro.org/Platform/QA/TestCases/IMX51EVK - Adding SATA,
Backlight, Touchscreen, Keypad, etc.
* [ImproveLinaroMediaCreate] port check_device to python:DONE.
* Submitted the hardware pack licence request to the TSC for approval.
Please let me know if you have any comments or questions.
Kind Regards,
Ian