stretch EOL point release (9.13) and 10.5 planning

2020-06-15 Thread Adam D. Barratt
Hi,

stretch transitions from oldstable-with-security-support to LTS support
on Saturday July 4th. As usual, we should aim for the final point
release to be soon after that, most likely pulling in any remaining
updates from security.d.o that are still in oldstable-new.

I think Saturday July 11th makes most sense (so freezing opu during the
transition weekend), but we could potentially stretch (no pun intended)
slightly further if need be.

We also need to look at the next buster point release in a similar
timeframe. Can anyone see a reason not to do the two at the same time,
as usual?

To get the ball rolling, please could you confirm your availability
for:

- July 11/12
- July 18/19

Thanks,

Adam



Re: stretch EOL point release (9.13) and 10.5 planning

2020-06-15 Thread Steve McIntyre
Hey Adam,

On Mon, Jun 15, 2020 at 05:44:54PM +0100, Adam Barratt wrote:
>Hi,
>
>stretch transitions from oldstable-with-security-support to LTS support
>on Saturday July 4th. As usual, we should aim for the final point
>release to be soon after that, most likely pulling in any remaining
>updates from security.d.o that are still in oldstable-new.
>
>I think Saturday July 11th makes most sense (so freezing opu during the
>transition weekend), but we could potentially stretch (no pun intended)
>slightly further if need be.
>
>We also need to look at the next buster point release in a similar
>timeframe. Can anyone see a reason not to do the two at the same time,
>as usual?

Should be fine for the images team.

>To get the ball rolling, please could you confirm your availability
>for:
>
>- July 11/12
>- July 18/19

Either is possible for me, with a slight preference for the second
weekend.

-- 
Steve McIntyre, Cambridge, UK.st...@einval.com
"Because heaters aren't purple!" -- Catherine Pitt



Re: stretch EOL point release (9.13) and 10.5 planning

2020-06-15 Thread Cyril Brulebois
Hi,

Adam D. Barratt  (2020-06-15):
> stretch transitions from oldstable-with-security-support to LTS support
> on Saturday July 4th. As usual, we should aim for the final point
> release to be soon after that, most likely pulling in any remaining
> updates from security.d.o that are still in oldstable-new.
> 
> I think Saturday July 11th makes most sense (so freezing opu during the
> transition weekend), but we could potentially stretch (no pun intended)
> slightly further if need be.
> 
> We also need to look at the next buster point release in a similar
> timeframe. Can anyone see a reason not to do the two at the same time,
> as usual?
> 
> To get the ball rolling, please could you confirm your availability
> for:
> 
> - July 11/12
> - July 18/19

Haven't looked at stretch in a while from a d-i point of view, but I
don't think we have any bugfixes pending? I'll have to check what's
happening on the buster front, if anything.

Anyway, I should be available, whatever date(s) get picked.


Cheers,
-- 
Cyril Brulebois (k...@debian.org)
D-I release manager -- Release team member -- Freelance Consultant


signature.asc
Description: PGP signature


Re: stretch EOL point release (9.13) and 10.5 planning

2020-06-15 Thread Andy Simpkins
On 15/06/20 19:05, Cyril Brulebois wrote:
> Hi,
> 
> Adam D. Barratt  (2020-06-15):
>> To get the ball rolling, please could you confirm your availability
>> for:
>>
>> - July 11/12
>> - July 18/19
> 
> 
> Anyway, I should be available, whatever date(s) get picked.
> 
Preferance would be the weekend of the 18/19 for Isy and me (we have
plans for the weekend before).

/Andy




signature.asc
Description: OpenPGP digital signature