Bob Proulx wrote:
> Lots still left to do for tomorrow.

Tomorrow the plan is something like:

Then migrate vcs0.  Which I expect to cause some pain.  Having tripped
on download0 due to the ssh keys blocking root login I think I can
avoid that for vcs0 now.  But it is a very busy system and will cause
some pain.

Then finish internal0's internal use IPv4 address over to the new
subnet.  Connections come in pairs so that is another round of
modifications on each of the clients.

Move the old vcs and olddownload IP addresses.  These need to move
after the NFS clients move.

Add IPv6 to frontend0.  Then I can say all of them have IPv6 addresses
and that should be simple.  But of the web config needs modifying to
use it however or it will cause web browsers to be very confused.

Update the NTP config all around for the new subnet.

Make sure resolv.conf is correct on the systems.  The old nameserver
addresses are accessible until the disconnection.

grep through /etc on all of the systems to make sure there aren't any
forgotten configuration using the old addresses.

Bob