Hi all,

All this talk about Enphase recently and I have a design question that I am
having trouble getting a straightforward answer to. The IQ system
controller can take up to 64A of PV AC output on the DER port (coming from
the IQ combiner for example). When there is more solar on site, the
question is what do you need to do with the rest of the solar.

They have a system planning guide that talks about some of this and you can
find it here:
https://enphase.com/download/planning-enphase-energy-system-tech-brief

Page 59 bullet point 6 says that with IQ8 micros, the excess PV must be
split into a grid-tied system. I recently did this, got a separate IQ
gateway, and a power line filter, and the system continues to have cross
talk issues between the two gateways, and the microinverters will just not
report properly no matter how many times tech support re-provisions the
devices and prevents each gateway from looking for more devices.

Then I noticed that with M series micros (page 62 bullet point 9) it says
that microinverters exceeding 64A can be added to the main panel. In this
scenario, there will be more than 64A of solar flowing through the IQ
system controller, even though the DER port is limited to 64A. I would like
to do something similar to this for my system with crosstalk issues and get
rid of the second IQ Gateway.

I asked tech support why there was a difference in the planning document
for IQ8 and for M series and whether I could add the extra IQ8 into the
backed up subpanel (This is a Sunlight backup system). They did not give me
a fully complete answer, but they did say this, "You can add the panels up
to 64A into the system controller and exceeding PV can be connected to the
backup subpanel."

I fear that this was a level 1 tech and that they may not have completely
understood the situation. This is the answer that I wanted, but I am not
sure I trust it yet. Has anyone here tried something similar to this?

Thanks!
-Dave

-- 

[image: Logo] <https://www.sungineersolar.com/>
Dave Tedeyan, P.E.
Owner | Sungineer Solar
p: he | him | his
a: 1653 Slaterville Rd. | Ithaca, NY 14850
w: www.sungineersolar.com <http://www.sungineersolar.com/>
c: (607) 270-0370
_______________________________________________
List sponsored by Redwood Alliance

Pay optional member dues here: http://re-wrenches.org

List Address: RE-wrenches@lists.re-wrenches.org

Change listserver email address & settings:
http://lists.re-wrenches.org/options.cgi/re-wrenches-re-wrenches.org

There are two list archives for searching. When one doesn't work, try the other:
https://www.mail-archive.com/re-wrenches@lists.re-wrenches.org/
http://lists.re-wrenches.org/pipermail/re-wrenches-re-wrenches.org

List rules & etiquette:
http://www.re-wrenches.org/etiquette.htm

Check out or update participant bios:
http://www.members.re-wrenches.org

Reply via email to