We have about 20 units out in service. 
All of the batteries SOC readings have drifted apart greatly.  IE always said 
not pay attention the battery readouts, and as long as voltage is even, that 
the batteries are working fine. 
After the last install we did of their batteries, their tech support group had 
me make up a cable to hook up a computer to the battery to re - set the BMS I 
believe.  
I’m scheduled with a new tech support channel for Iron Edison to take this on. 
Has anyone done this before , and is it really going to do any good ?  



Jeremy Rodriguez 
Solar Installation / Design
All Solar, Inc.
1453 M St. 
Penrose Colorado 81240

Sent by Jeremy's iPhone. Sorry for typos and shorthand. 
_______________________________________________
List sponsored by Redwood Alliance

Pay optional member dues here: http://re-wrenches.org

List Address: RE-wrenches@lists.re-wrenches.org

Change listserver email address & settings:
http://lists.re-wrenches.org/options.cgi/re-wrenches-re-wrenches.org

There are two list archives for searching. When one doesn't work, try the other:
https://www.mail-archive.com/re-wrenches@lists.re-wrenches.org/
http://lists.re-wrenches.org/pipermail/re-wrenches-re-wrenches.org

List rules & etiquette:
http://www.re-wrenches.org/etiquette.htm

Check out or update participant bios:
http://www.members.re-wrenches.org

Reply via email to