Al, See 250.2: “Bonding Jumper, Supply-Side. A conductor installed on the supply side of a service or within a service equipment enclosure(s), or for a separately derived system, that ensures the required electrical conductivity between metal.”
rick brown SolShine Energy Alternatives, LLC Electrical & Solar Contracting Services www.SolShineEnergyAlternatives.com Check, Virginia 24072 540.808.9502 VA Class A Contractor Lic# 2705147660 VA Master Electrician Lic# 2710062762 VA Alternative Energy Systems Installer NABCEP Certified PV Installation Professional 110112-21 > On Jul 23, 2019, at 9:38 AM, Al Frishman <evolvedso...@gmail.com> wrote: > > Hey Wrenchers, > I have been having a design debate with several associates regarding bonding > the Neutral to the Ground for Line Side grid connections. > > In the fused solar AC Disconnect located closest to the Service Line Side > grid connection should the Neutral be bonded to Ground? What Article in the > NEC defines the requirement. > > As always your feedback is appreciated. > > Al Frishman > EvolvedSolar > (917) 699-6641 > > _______________________________________________ > List sponsored by Redwood Alliance > > List Address: RE-wrenches@lists.re-wrenches.org > > Change listserver email address & settings: > http://lists.re-wrenches.org/options.cgi/re-wrenches-re-wrenches.org > > List-Archive: > http://www.mail-archive.com/re-wrenches@lists.re-wrenches.org/maillist.html > > List rules & etiquette: > www.re-wrenches.org/etiquette.htm > > Check out or update participant bios: > www.members.re-wrenches.org >
_______________________________________________ List sponsored by Redwood Alliance List Address: RE-wrenches@lists.re-wrenches.org Change listserver email address & settings: http://lists.re-wrenches.org/options.cgi/re-wrenches-re-wrenches.org List-Archive: http://www.mail-archive.com/re-wrenches@lists.re-wrenches.org/maillist.html List rules & etiquette: www.re-wrenches.org/etiquette.htm Check out or update participant bios: www.members.re-wrenches.org