For Rapid Shutdown, I started using Midnite's BOS system, it can be set up on a string level or module level (2019) with enough receivers.  While it doesn't work with most charge controllers right now, it does work with the Magnum PT100 oddly enough.  We haven't had any glitches, the RS worked with very little fanfare. My biggest peeve is that the transmitter either runs on 120 vac or 12 vdc, so we set up a DC to DC converter.  Midnite really needs 24 v and 48 v versions of the transmitter. I don't want to use 120 vac, because then array charging becomes dependent on inverter operation.  If the inverter shuts down due to low battery, you're back into the battery death spiral problem inherent to AC coupled systems.
Ray Walters
Remote Solar
303 505-8760
On 11/23/18 8:40 PM, Kienan Maxfield wrote:
I'm not quite sure on the Rapid Shut Down. I am quite sure that they 
have a compatible Rapid Shut Down solution that will suffice for about 
1 month and 7 days but after 2019................................. I'm 
not quite sure what we'll do... If anyone else can answer this 
question, that would be awesome!

-Kienan

_______________________________________________
List sponsored by Redwood Alliance

List Address: RE-wrenches@lists.re-wrenches.org

Change listserver email address & settings:
http://lists.re-wrenches.org/options.cgi/re-wrenches-re-wrenches.org

List-Archive: 
http://www.mail-archive.com/re-wrenches@lists.re-wrenches.org/maillist.html

List rules & etiquette:
www.re-wrenches.org/etiquette.htm

Check out or update participant bios:
www.members.re-wrenches.org

Reply via email to