We're considering moving away from concrete footings where appropriate on GM 
projects. I am have not used any helical anchor systems and am curious about 
the efficiency of the helical anchor system in resi applications. Specifically, 
am I going to need soil compaction tests and/or geo survey with a P.G. stamp? 
What is the AHJ going to be looking for? As always, I appreciate any input! 
 
Eric Stikes
Founding Director & CEO
Good Sun Solar, A CA non-profit corp.
www.goodsun.life