Wrenchers, What is the requirement for fusing 2 strings per MPPT? Specifically for an inverter like the Fronius Primo that has no integrated fuses. If you run 2 strings to each MPPT do you need to fuse each string? In this case there is a total of 4 strings which would need to be fused if using a single mppt.
If the home runs are run in separate conduits from the array to limit the strings in the conduit to 2 per you still have all 4 strings together in the inverter. All thoughts and feedback are appreciated. Al Frishman AeonSolar (917) 699-6641 - cell (888) 460-2867 www.aeonsolar.com
_______________________________________________ List sponsored by Redwood Alliance List Address: RE-wrenches@lists.re-wrenches.org Change listserver email address & settings: http://lists.re-wrenches.org/options.cgi/re-wrenches-re-wrenches.org List-Archive: http://www.mail-archive.com/re-wrenches@lists.re-wrenches.org/maillist.html List rules & etiquette: www.re-wrenches.org/etiquette.htm Check out or update participant bios: www.members.re-wrenches.org