By the time we took the Sanyo’s down 7 out of 12 had varying degrees of Voc, either 25%, 50%, 75% of full Voc., in a nut shell. This didn’t just happen all at once, since we started diagnostics in the fall, then got snowed out, and resumed in the spring with the system showing less output.
Panasonic would not warrantee them after a very long drawn out warranty claim documentation process. So the Japanese engineers from Panasonic claimed it to be transient lightning surge. Not covered under warranty. This was a SMA SB2500 two strings of 6 system originally. There was no visual damage on the front of burnt traces and the sort of discoloring that we’ve seen with the BP160’s and such. Didn’t affect the SB2500, AC & DC switch gear and CB’s, 600VDC RK5 fuses, Delta LA 602’s, Wattsun AZ225 tracker eye or motors, or 24 VDC power supply, no burned grounding conductors. Hmmm… I couldn’t disprove them…. We only did this one 195BA3 system having installed the 190’s prior, and the 200’s after it. We don’t have others to compare notes to, wondering if others here have had similar issues with the Sanyo 195 BA3 modules? Chris Worcester Solar Wind Works NABCEP Certified PV Installer Office 530-582-4503 Cell 530-448-9692 Fax 530-582-4603 www.solarwindworks.com ch...@solarwindworks.com From: RE-wrenches [mailto:re-wrenches-boun...@lists.re-wrenches.org] On Behalf Of Ken Schaal Sent: Thursday, December 17, 2015 10:09 AM To: RE-wrenches; ken schaal Subject: Re: [RE-wrenches] Module recommendation for a specific off grid situation Do you have any specifics as to why the Sanyos's were failing ? Thanks, Ken On Dec 17, 2015 12:54 PM, "Chris Worcester" <ch...@solarwindworks.com> wrote: We just got a dozen from CivicSolar last month for a Sanyo replacement on an existing Wattsun AZ225. Nice boost in power, seeing 270 watts output from each 240 watt module on the APsystems YC500A microinverters. It was a cold day! Took off Sanyo 195 BA3’s that were failing big time. Chris Worcester Solar Wind Works NABCEP Certified PV Installer Office 530-582-4503 Cell 530-448-9692 Fax 530-582-4603 www.solarwindworks.com ch...@solarwindworks.com From: RE-wrenches [mailto:re-wrenches-boun...@lists.re-wrenches.org] On Behalf Of Starlight Solar Power Systems Sent: Thursday, December 17, 2015 7:29 AM To: RE-wrenches Subject: Re: [RE-wrenches] Module recommendation for a specific off grid situation I have been trying to purchase Panasonic modules for years. Where do you get them? Thank you, Larry Crutcher Starlight Solar Power Systems On Dec 17, 2015, at 12:27 AM, Chris Worcester <ch...@solarwindworks.com> wrote: Hi Allan, Try the Panasonic 240’s Chris Worcester Solar Wind Works NABCEP Certified PV Installer Office 530-582-4503 Cell 530-448-9692 Fax 530-582-4603 www.solarwindworks.com ch...@solarwindworks.com _______________________________________________ List sponsored by Redwood Alliance List Address: RE-wrenches@lists.re-wrenches.org Change listserver email address & settings: http://lists.re-wrenches.org/options.cgi/re-wrenches-re-wrenches.org List-Archive: http://www.mail-archive.com/re-wrenches@lists.re-wrenches.org/maillist.html List rules & etiquette: www.re-wrenches.org/etiquette.htm Check out or update participant bios: www.members.re-wrenches.org
_______________________________________________ List sponsored by Redwood Alliance List Address: RE-wrenches@lists.re-wrenches.org Change listserver email address & settings: http://lists.re-wrenches.org/options.cgi/re-wrenches-re-wrenches.org List-Archive: http://www.mail-archive.com/re-wrenches@lists.re-wrenches.org/maillist.html List rules & etiquette: www.re-wrenches.org/etiquette.htm Check out or update participant bios: www.members.re-wrenches.org