Hi Esteemed Wrenchies,

For a totally off-grid AC Coupled Sunny Island system to control an off-grid Kohler two-wire start generator  I assume:

1) All I need to bring is control wire besides the genny and Sunny Island.

2) No external relays needed - all built in to the Sunny Island and genny.

3)  If no grid-tie (only generator)  then no need to program DIGIN signal as per SMA's tech note on Gen and grid systems?

Am I missing something here?

Thanks!

Jeff
--
 
Jeff Clearwater
Ecovillage Network of the Americas
The Visionary Commons
Ecovillage Design Consultant
www.visionarycommons.org
skype - jclearwater
cell - 413-559-9763


~~~~~~~~~~~~~~~~~~~~~~~~~~~

--
Jeff Clearwater
Village Power Design
Renewable Energy Design & Installation
Ecovillage Design Consultant

NABCEP™ Certified Solar PV Installer
Licensed Solar Contractor in CA - C-46
www.villagepower.com
413-559-9763
~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~

_______________________________________________
List sponsored by Home Power magazine

List Address: RE-wrenches@lists.re-wrenches.org

Change email address & settings:
http://lists.re-wrenches.org/options.cgi/re-wrenches-re-wrenches.org

List-Archive: http://lists.re-wrenches.org/pipermail/re-wrenches-re-wrenches.org

List rules & etiquette:
www.re-wrenches.org/etiquette.htm

Check out participant bios:
www.members.re-wrenches.org

Reply via email to