Friends:
I have had plan checkers insist I use wet rated wire on rooftops even
though the wire was in either liquid tight or EMT with raintight
connectors. I did not need to dispute this because we had specified THHN
wire that is also rated THWN for wet locations. This discussion makes me
think I should have contradicted the requirement because I am not sure wet
rated wire is required inside dry conduit. I will be looking this up.
I feel that you should not let an AHJ impose a requirement that is not in
the code because then you become bound to the new stricture. I realize
that an AHJ can impose stricter requirements, but I insist that it be in
writing, required in advance of the job in question and that it be required
universally. Otherwise, it's anarchy.
William Miller
Miller Solar
Voice :805-438-5600
email: will...@millersolar.com
http://millersolar.com
License No. C-10-773985
_______________________________________________
List sponsored by Home Power magazine
List Address: RE-wrenches@lists.re-wrenches.org
Options & settings:
http://lists.re-wrenches.org/options.cgi/re-wrenches-re-wrenches.org
List-Archive: http://lists.re-wrenches.org/pipermail/re-wrenches-re-wrenches.org
List rules & etiquette:
www.re-wrenches.org/etiquette.htm
Check out participant bios:
www.members.re-wrenches.org