Note that the language states min. service disconnect size, and not 
specifically the size of the service. In the old days we would go round and 
round w/the AHJ over this in OTG systems. In most cases we could point to the 
"Service Disconnect" that was rated at least 100A this being the Main DC 
breaker while the AC output rarely exceeded 30A @ 120V. However, some did not 
buy this and wanted 100A of delivered service, at this point here in CA we 
would have to fall back to Class K regs. This was created to accommodate the 
numerous OTG homes and cabins that could never meet the conventional UBC 
standards. Our home was the 1st court test case in the state as at the time a 
geodesic dome would not meet local codes even though we had blueprints stamped 
by Bucky Fuller himself. Interestingly, their main issue was that they could 
not determine where to draw the line between what was wall and roof!


>From the Solar, Wind and Hydro powered office of Jeff Oldham/Regenerative 
>SOLutions
____________________________________________________________
Obama Urges Homeowners to Refinance
If you owe under $729k you probably qualify for Obama's Refi Program
http://thirdpartyoffers.juno.com/TGL3131/4c77eba71bcf694aa4ast02vuc
_______________________________________________
List sponsored by Home Power magazine

List Address: RE-wrenches@lists.re-wrenches.org

Options & settings:
http://lists.re-wrenches.org/options.cgi/re-wrenches-re-wrenches.org

List-Archive: http://lists.re-wrenches.org/pipermail/re-wrenches-re-wrenches.org

List rules & etiquette:
www.re-wrenches.org/etiquette.htm

Check out participant bios:
www.members.re-wrenches.org

Reply via email to