Dana,

Could you tell me a bit more about that 100' tower?
The last I knew, SWWP only offered a 70' tower. So this would be a 3rd party tower?
Xzeres (formerly ARE)? Or LMW&S? And is that schedule 40 pipe or schedule 10?

Did you install the concrete foundations? Since you've installed some tilt towers before,
I would imagine you understand the importance of having the foundations line up correctly.
For this reason, I hate finishing a tower installation someone else started! I've seen as much
as a 6 foot difference in elevation between the two side anchors on owner installed foundations.

Under ideal circumstances and on that mythical frictionless plane, I'd allot 1 day with 3
people for assembly and another day with 4 people during the initial raising of the empty tower
and the final raising with the cherry on top. Having a side spotter on these towers is invaluable!

The trick of course is knowing all the unknowns before hand ;-)

Roy Butler
NABCEP Certified Solar PV Installer®
NYSERDA eligible PV & wind installer
PA Sunshine Program Approved PV Installer
Four Winds Renewable Energy, LLC
8902 Route 46
Arkport, NY 14807
607-324-9747

www.four-winds-energy.com

Although no trees were killed in the sending of this message, 
a large number of electrons were terribly inconvenienced.

                

On 7/30/2010 11:23 AM, Dana wrote:

Good Morning all,

 

I have an ongoing client that we have straightened out the doings of the first 3 PV installers.

 

They have a Skystream Wind Generator, concrete bases are in place and a 100’ tower kit, but not the tower pipe sections.  We are just starting to look at the erection process of this.

 

Has anyone erected a 100’ tower for a Skystream wind generator?

I have done 100’ tilt up towers in the past but not for this size of a wind generator.

 

If so, how many man-hours would you allot for the assembly of the tower on the ground and raising?

Assuming all goes smoothly and a worst case.

I am aware of having to 20’ - “gin-pole” the 50’ gin-pole, and have several tractors to move the pipe around.

 

 

Thanks,  Dana Orzel

 

Great Solar Works, Inc

E - d...@solarwork.com

V - 970.626.5253

F - 970.626.4140

C - 970.209.4076

web - www.solarwork.com

 

"Responsible Technologies for Responsible People since 1988"

 

_______________________________________________ List sponsored by Home Power magazine List Address: RE-wrenches@lists.re-wrenches.org Options & settings: http://lists.re-wrenches.org/options.cgi/re-wrenches-re-wrenches.org List-Archive: http://lists.re-wrenches.org/pipermail/re-wrenches-re-wrenches.org List rules & etiquette: www.re-wrenches.org/etiquette.htm Check out participant bios: www.members.re-wrenches.org
_______________________________________________
List sponsored by Home Power magazine

List Address: RE-wrenches@lists.re-wrenches.org

Options & settings:
http://lists.re-wrenches.org/options.cgi/re-wrenches-re-wrenches.org

List-Archive: http://lists.re-wrenches.org/pipermail/re-wrenches-re-wrenches.org

List rules & etiquette:
www.re-wrenches.org/etiquette.htm

Check out participant bios:
www.members.re-wrenches.org

Reply via email to