I just put some proposed dates into the 7.1 schedule page: https://wiki.qemu.org/Planning/7.1#Release_Schedule
* 2022-07-12 Softfreeze * 2022-07-19 Hardfreeze. Tag rc0 * 2022-07-26 Tag rc1 * 2022-08-02 Tag rc2 * 2022-08-09 Tag rc3 * 2022-08-16 Release; or tag rc4 if needed * 2022-08-23 Release if we needed an rc4 Does this work for people? I just worked backwards from a final release date about 4 months after 7.0; easy enough to shift it forward or back by a week or so if that works better for some reason. thanks -- PMM