The jobs on Cirrus-CI sometimes get delayed quite a bit, waiting to
be scheduled, so while the build test itself finishes within 60 minutes,
the total run time of the jobs can be longer due to this waiting time.
Thus let's increase the timeout on the gitlab side a little bit, so
that these jobs are not marked as failing just because of the delay.

Signed-off-by: Thomas Huth <th...@redhat.com>
---
 .gitlab-ci.d/cirrus.yml | 1 +
 1 file changed, 1 insertion(+)

diff --git a/.gitlab-ci.d/cirrus.yml b/.gitlab-ci.d/cirrus.yml
index e7b25e7427..22d42585e4 100644
--- a/.gitlab-ci.d/cirrus.yml
+++ b/.gitlab-ci.d/cirrus.yml
@@ -14,6 +14,7 @@
   stage: build
   image: registry.gitlab.com/libvirt/libvirt-ci/cirrus-run:master
   needs: []
+  timeout: 80m
   allow_failure: true
   script:
     - source .gitlab-ci.d/cirrus/$NAME.vars
-- 
2.27.0