Hi David,

On Wed, Oct 04, 2017 at 01:44:38PM -0700, David McBride wrote:
> Here's what (I think) I know about what must be done when we branch.
> Please correct and fill in the details, including who owns the task.  Also,
> please comment on whether a task can be done in advance of branching.
> 
>    1. Update docker yaml file
>    2. Enable testing (RELENG repo)
>    3. Create Jenkins jobs for branch for each installer

To clarify Jenkins jobs need to be made for all projects not just
installers.

Creating the branch specific Jenkins jobs is owned by Releng and this is
the specific activity I mentioned could be automated before the branch
is made. 

>    4. Update the test results dashboard
> 
> I think that we can shave at least a week off of this process.  That, in
> combination with pulling MS7 in by a week should give our team sufficient
> time to complete the release.  I appreciate your input.
> 
> David
> 
> -- 
> *David McBride*
> Release Manager, OPNFV
> Mobile: +1.805.276.8018
> Email/Google Talk: [email protected]
> Skype: davidjmcbride1
> IRC: dmcbride

Attachment: signature.asc
Description: PGP signature