On Wed, Jun 28, 2017 at 11:11:12AM -0700, David McBride wrote:
> TSC,
> 
> After examining status and considering various alternatives, Ray and I have
> agreed to propose July 14 as the new release date for Danube 3.  We believe
> that this will give project and installer teams time to overcome current
> issues, as well as allowing us to avoid the 4th of July holiday in the U.S.,
> when many community members will be away on vacation.
> 
> Assuming that the TSC approves this change, then I would suggest the following
> schedule:
> 
>   • July 12 - complete testing
>   • July 13 - finish document updates / update JIRA
>   • July 14 - tag repos and release
>   • Week of July 17 - download page goes live
> 
> TSC members, please respond to this email with your vote on the following by
> EOD PT June 30:
> 
> 
>     Does the TSC approve moving the Danube 3.0 release date to July 14th? (+1,
>     0, -1)
> 
> 
> David
> 
> --
> David McBride
> Release Manager, OPNFV
> Mobile: +1.805.276.8018
> Email/Google Talk: dmcbr...@linuxfoundation.org
> Skype: davidjmcbride1
> IRC: dmcbride