David,
One thing to keep in mind, there are at least 2 major events that could
affect the "Planning Complete" and "Scenarios Defined" milestones, which
are the ODL summit, the week of September 25th and the OpenStack summit
in Barcelona, the week of October 25th.
Regards,
Brady
On 09/09/16 00:45, David McBride wrote:
Team,
I've posted an update to the schedule
<https://wiki.opnfv.org/download/attachments/6827418/OPNFV%20Release%20%2522D%2522%20r2.pdf?version=1&modificationDate=1473367413338&api=v2>.
Please review and provide feedback.
Note: during the release meeting on Tuesday, we discussed removing
the JIRA milestone, since it was not considered release gating. Since
then, I've changed my mind. For the D-release, I expect that we will
have implemented our JIRA processes sufficiently that we will be able
to rely on JIRA to understand project status. Therefore, it is
appropriate to believe that if we still have unresolved JIRA issues
assigned to the release, then the release is not complete. We will be
discussing exactly how this will be accomplished in the coming weeks.
David
--
*David McBride*
Release Manager, OPNFV
Mobile: +1.805.276.8018 <tel:%2B1.805.276.8018>
Email/Google Talk: [email protected]
<mailto:[email protected]>
Skype: davidjmcbride1
IRC: dmcbride
_______________________________________________
opnfv-project-leads mailing list
[email protected]
https://lists.opnfv.org/mailman/listinfo/opnfv-project-leads
_______________________________________________
opnfv-tech-discuss mailing list
[email protected]
https://lists.opnfv.org/mailman/listinfo/opnfv-tech-discuss