Current Dev Position: YP 2.6 M4 is in QA.

Next Deadline: YP 2.6 M4 Release Target was Oct. 26, 2018


SWAT Team Rotation:

·         SWAT lead is currently: Chen

·         SWAT team rotation: Chen  -> Armin on Nov. 9, 2018

·         SWAT team rotation: Armin -> Paul on Nov. 16, 2018

·         https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team


Key Status/Updates:

·         YP 2.6 M4 rc1 is in QA, 95% completed, and the current status can be 
viewed at: 
https://wiki.yoctoproject.org/wiki/index.php?title=WW44_-_2018-10-30_-_Full_Test_Cycle_2.6_M4_RC1

·         There are a number of good bug and CVE fixes queued in master-next 
which makes an rc2 possible although its likely these would merge to thud 
immediately after release instead due to how far behind schedule we now are.

·         A problem with the way the Yocto Project Compatibility tests are 
being run was identified as it was possible to fail the BSP compatibility tests 
if the machine option was specified. There is a fix for OE-Core in master-next 
but we need to likely improve the way the test is being run for that to ensure 
everyone is using it consistently.

·         At ELC-E/OEDEM, issues were mentioned to do with the completeness of 
the source mirror. Issues were identified by Michael and Richard and the source 
mirroring should be working properly again, including supporting http only 
builds. A new test has been added to the autobuilder to ensure this does not 
regress.

·         Patches are queuing up in master-next right now, ready for when we 
start taking patches for the 2.7 development cycle, but a number will also 
likely merge to the thud branch as they’re useful bug or CVE fixes.


Planned Releases for YP 2.6:

·         YP 2.6 M4 Build is in QA

·         YP 2.6 M4 Release Target was Oct. 26, 2018


Planned upcoming dot releases:

·         YP 2.4.4 (Rocko) will be targeted after YP 2.6 M4 is done.

·         YP 2.5.2 (Sumo) will be targeted after YP 2.4.4 is done.


Tracking Metrics:

·         WDD 2369 (last week 23867) 
(https://wiki.yoctoproject.org/charts/combo.html)

·         Poky Patch Metrics

o    Total patches found: 1692 (last week 1690)

o    Percentage of patches in the Pending State: 739 (44%) [last week 739 (44%)]


Key Status Links for YP:

https://wiki.yoctoproject.org/wiki/Yocto_Project_v2.6_Status

https://wiki.yoctoproject.org/wiki/Yocto_2.6_Schedule

https://wiki.yoctoproject.org/wiki/Yocto_2.6_Features

https://wiki.yoctoproject.org/wiki/Yocto_Project_v2.7_Status

https://wiki.yoctoproject.org/wiki/Yocto_2.7_Schedule

https://wiki.yoctoproject.org/wiki/Yocto_2.7_Features


The Status reports are now stored on the wiki at: 
https://wiki.yoctoproject.org/wiki/Weekly_Status


[If anyone has suggestions for other information you’d like to see on this 
weekly status update, let us know!]

Thanks,

Stephen K. Jolley
Yocto Project Program Manager
INTEL, MS JF1-255, 2111 N.E. 25th Avenue, Hillsboro, OR 97124
•    Cell:                (208) 244-4460
• Email:                             stephen.k.jol...@intel.com

-- 
_______________________________________________
Openembedded-core mailing list
Openembedded-core@lists.openembedded.org
http://lists.openembedded.org/mailman/listinfo/openembedded-core

Reply via email to