On Sun, 27 Mar 2011 12:54:52 CDT, Jima said:
> On 3/27/2011 12:10 PM, Zaid Ali wrote:
> > On 3/27/11 8:19 AM, "[email protected]"<[email protected]>
> > wrote:
> >> There's only one question to be asked - will the (possibly new) upstream
> >> of the moved datacenter announce the route for the /24 or not?
> >
> > Why would the new upstream refuse to announce the /24 assuming he has the
> > correct information for his route objects and visible through the RIR
> > database.
> 
>   Some transit providers dislike announcing smaller networks, and thus 
> have lower limits.

Which is why I said you need to find a willing upstream.  And yes, if Mark
moving into a monopoly area, he'll probably have to do it the way the monopoly
wants it done.