Hi, grizz. I have to ask for a little more information. Does Y always 
happen two weeks after X?  

Task Y apparently starts and is due all on the same day. Is the same true 
of X, or dues X actually involve some lead time?

A lot of times when people are using "reoccurs one month after completion" 
rather than "reoccurs every one month" it is because the task does not 
reliably get done when scheduled. Some times it might happen every month, 
other times there might be a few months elapsed before it gets done. Is 
that what's happening for you?

In this scenario, the "one month" is like a minimum wait time. After you do 
X, you may not do it again the next day or the next week, you have to wait 
a month.What happens if you do X on January 1 and Y has start and due date 
January 15 but you do not get around to doing Y until Feb 7. Does X happen 
again on Feb 1 or does it have to wait for Y to happen? If X happens on Feb 
1 does Y get rescheduled for Feb 15 or does it remain overdue for Jan 15? 
After Y happens on Feb 7 is the next Y Feb 15 (two weeks after X) or Mar 7 
(a month after Y) or both?

The scenario is a little confusing to me because there are two different 
formulas for scheduling Y and I don't know what to do if they give 
different results. If you can explain how this would be supposed to work, I 
will try to see hoe that could be coded.

-Dwight

On Thursday, January 4, 2018 at 3:12:33 AM UTC-5, grizz wrote:
>
> Hi,
>
> I want to have two task:
>
> X - reoccurs month after completition
> Y - reoccurs month after completition and it's start/due date should be 2 
> weeks after completion of X.
>
> How can I achieve this?
>

-- 
You received this message because you are subscribed to the Google Groups 
"MyLifeOrganized" group.
To unsubscribe from this group and stop receiving emails from it, send an email 
to [email protected].
To post to this group, send email to [email protected].
Visit this group at https://groups.google.com/group/mylifeorganized.
To view this discussion on the web visit 
https://groups.google.com/d/msgid/mylifeorganized/25a83a2a-6a21-4433-8751-5267b74a64d0%40googlegroups.com.
For more options, visit https://groups.google.com/d/optout.

Reply via email to