Hello Eberhard, Dwight
Thank you for your kind help !
I want to post a link to an old uservoice request here:
http://mlo.uservoice.com/forums/9235-general/suggestions/1114967-inheritance-on-all-goals-not-just-week-goals
Although i think that the suggestion mentioned by Dwight in the previous 
post (“TaskHasGoal” and “BranchHasGoal” filters) is better.
Best regards
Andrei B

суббота, 20 сентября 2014 г., 11:41:45 UTC+3 пользователь Eberhard написал:
>
> Hi Andrew,
>
> things look to me as follows ... 
>
> ONLY the weekly goal seems to get inherited to sbtask, but neither monthly 
> goal nor yearly goal.
>
> But it's NOT ONLY the red "!" that is inherited, but also the goal itself.
>
> I'm creating a task and a subtask and I'm marking the (parent) task as 
> weekly goal.
>
> I'm getting the red "!" for both taks (parent and sub-task) but only for 
> the parent task you'll find "weekly goal" in properties pane properly 
> activated (not for the sub-task).
>
> However ... define a simple rule for auto-formatting (goal=week) and have 
> an icon be set for all tasks that apply to that auto-formatting rule ... 
> you'll get both tasks (parent and sub-task) be iconized (means to me ... 
> both task are "internally marked" as weekly goals).
>
> According to me all this is not correctly implemented.
>
> (a) I do not like the fact at all, that subtasks are automatically marked 
> as weekly goals once their parent is a weekly goal.
>
> (b) It's at least confusing to having sub-tasks automatically marked as 
> weekly goals while the relevant button in properties pane indecates that 
> gould = none.
>
> Eberhard 
>
> On Sat, Sep 20, 2014 at 4:08 AM, Dwight Arthur <[email protected] 
> <javascript:>> wrote:
>
>> Hi, Andrew.
>> Are you certain?
>>
>> I created a new blank profile and added three tasks, each of which has 
>> three second-level subtasks, and each of them contains three third-level 
>> subtasks.  I marked one second-level tasks as goal:week. The display showed 
>> four tasks marked with red "!" - the second level task I had set for goal, 
>> and the three third-level tasks that are subtasks of the goal task. However 
>> it is not true that the three third level tasks inherited the goal from 
>> their second level parent. The three third level tasks despite their red 
>> "!" show in task properties as goal:none. My conclusion is that the goal 
>> itself is not inherited but that the red "!" is set for tasks that have 
>> a weekly goal or tasks that live in a hierarchy below a task with weekly 
>> goal (with no intermediary tasks with goals other than none and week)..
>>
>> In further testing I created a new subtask under the goal task. Like the 
>> three other subtasks it shows the red "!" but the task properties showed 
>> goal:none.
>>
>> For the other part, I agree with you that I said it backwards. The 
>> Goalmaster filter will pass only those tasks that are actually set to the 
>> specified goal, with no consideration of inheritance. The Goal filter on 
>> the other hand, will pass any task that has the specified goal setting, as 
>> well as the entire branch of subtasks under that task, but excluding any 
>> subtask that has a different goal set (other than goal:none) and excluding 
>> any branch of subtasks under the excluded task.
>>
>> On Wednesday, September 17, 2014 2:35:04 PM UTC-4, Andrei wrote:
>>>
>>> Hello Dwight
>>> Thank you for pointing me into the right direction.
>>>
>>> By default, the child tasks are inheriting the Goal from its parent.
>>> If we want the view to show only the Parent task, then we may use Goal 
>>> Master.
>>> (filtering by Goal will return the parent + the child).
>>>
>>> Best regards
>>> Andrew
>>>
>>  -- 
>> You received this message because you are subscribed to the Google Groups 
>> "MyLifeOrganized" group.
>> To unsubscribe from this group and stop receiving emails from it, send an 
>> email to [email protected] <javascript:>.
>> To post to this group, send email to [email protected] 
>> <javascript:>.
>> Visit this group at http://groups.google.com/group/mylifeorganized.
>> To view this discussion on the web visit 
>> https://groups.google.com/d/msgid/mylifeorganized/fb39bdf9-e8b8-4535-97d9-ac80cc4c25ab%40googlegroups.com
>>  
>> <https://groups.google.com/d/msgid/mylifeorganized/fb39bdf9-e8b8-4535-97d9-ac80cc4c25ab%40googlegroups.com?utm_medium=email&utm_source=footer>
>> .
>>
>> For more options, visit https://groups.google.com/d/optout.
>>
>
>

-- 
You received this message because you are subscribed to the Google Groups 
"MyLifeOrganized" group.
To unsubscribe from this group and stop receiving emails from it, send an email 
to [email protected].
To post to this group, send email to [email protected].
Visit this group at http://groups.google.com/group/mylifeorganized.
To view this discussion on the web visit 
https://groups.google.com/d/msgid/mylifeorganized/6cca2bfd-af5f-4980-87e9-41816513c6be%40googlegroups.com.
For more options, visit https://groups.google.com/d/optout.

Reply via email to