+1 on B.
Realistically trunk is in a pseudo freeze anyway since mostly every
committer should be focused on 1.1 bug fixes. Since there will likely be
minimal commits to trunk, the chances for conflicts is less likely. In
the case of the canadian swat team, you'll likely be the one who commits
these changes so, as you noted, it should be your decision whether to
add these to a branch instead. What are we gaining from freezing trunk
after the 1.1 fixes merge rather than freezing it now?
Either approach will delay 1.2 development, but B will increase the
likelihood of a quicker 1.1 release. We agreed on B before and although
it certainly isn't ideal, we should stick with it. The downside with B
is that we'll need to run diffs on the modules and designate a RM for
each module to work through any merge problems. I don't think we can
expect one person to take on this work. After the merge, do we need
some semblance of QA on trunk to make sure it works (or doesn't work) as
expected? I think so. I agree that freezing trunk is inevitable, so
developers working 1.2 will need to branch an remerge after the freeze.
Regarding A, as Josh noted, it'll be a pain for developers to backport
fixes immediately. Also in an ideal world, in scenario A, developers
should run integration tests and confirm bamboo passed after each merge
which would also be a burden.
Regarding "marked" issues, all things that aren't set for fix version
1.1.x that are currently being worked on should use version 1.2.
Affects version should be 1.1.
On 1/25/11 8:47 AM, Christopher Brooks wrote:
My understanding is that:
-Fixes to things marked as 1.1 bugs go onto branch.
-Fixes to things not marked as 1.1 bugs (either new features or bugs in
things that are not for 1.1) go to trunk.
-Committers can choose to use private branches for whatever they want
to.
This, from my understanding, is in line with almost every other project
I've seen. Freezing trunk for the whole time we are preparing a
release is not something I've ever seen, but it's another option that
was brought up.
The question is then:
1. Are backports from the 1.1 branch merged to trunk immediately or
once 1.1 is release?
a). If (1==immediately), who does it, the RM or the dev who committed
it? The implication, as Josh noted, that if it is the dev then they
need to have two environments setup.
b). If (1!=immediately), who does it at the end?
Suggestion that if we do (b) we could freeze trunk for, say, a week,
and then have individuals manually merge changes based on diffs of
branch and trunk (not patchsets).
Can we have some rapid discussion/turnaround so we can get a process
approved and up on our wiki?
Chris
_______________________________________________
Matterhorn mailing list
[email protected]
http://lists.opencastproject.org/mailman/listinfo/matterhorn
To unsubscribe please email
[email protected]
_______________________________________________