On Sun, Nov 23, 2003 at 11:42:46PM +0100, Michael Schmitt wrote:
> Hello everybody,
> 
> we planned to release LyX 1.4 on Christmas, didn't we? Well, that's in 
> just 30 days...

This was assuming that four people fix three bugs per week each or
so...

> So, what is the current schedule? Last week, Andre told me that there is 
> still some work left concerning the core. I am wondering what else is 
> missing... (missing dialogs, major broken features, tex2lyx 
> deficiencies, ...???)

I think it's really just glueing shards together now.
 
> Provided that the only problems are in the LyX core, we should think 
> about a feature freeze and a message freeze.

Message freeze and a slight feature freeze might be ok (i.e. no
arbitrary change of features, but a new inset or so is in order...)

> Due to the many changes (UI-wise), it would be nice if the manual
> writers and translators were able to start their work a few weeks
> ahead of the release date.

I think this is a good idea.

Andre'