Scott Kostyshak wrote:
> On Mon, Jan 08, 2018 at 06:42:41PM +0000, Pavel Sanda wrote:
> > Hi Juergen,
> > 
> > I don't know if there is still any energy left on your side, but even short 
> > time
> > work with outliner and beamer shows that the new system breaks one of the 
> > cool
> > features we had - reorganizing slide order via outliner's buttons up/down :(
> > 
> > We can start with this one:
> > 1. open beamer manual & outliner
> > 2. go to the first frame
> > 3. hit outliner "down" button.
> > 4. 1&2nd slide merge together
> 
> The recipe above seems to not be a regression from what I can tell. I can
> reproduce with 2.2.0. But it sounds like you found other similar issues
> that are a regression?

I mean regression to previous beamer implementation from which we departed at 
2.1
(I worked mainly under 2.0 until recent JMarc painting patch) so I apologize
if my complaints did not come earlier :)


Another slide-merging problem at the end of beamer documents, likely because of
missing horizontal ending of the last frame.
1. open beamer manual & outliner
2. go to any frame
3. try to move it to last position via outliner "down" button.
4. it merges into last slide

> > I have in my pockets example when only moving section down works, but not 
> > up.
> > Playing with it for a while produces crash, it might take a while to 
> > produce MWE
> > but I try to come with it within couple days.
> 
> OK hopefully we can figure that out.

As it usually happens it all happened during the rush hours of finalizing my 
talk
and now I can't reproduce the neither of two above problem. Will keep trying...

Pavel

Reply via email to