Thank you for the update!!
> On Jun 24, 2024, at 6:17 PM, C Eliot <empiremaster...@gmail.com> wrote:
> 
> The official ruling from MEPA this afternoon requires the Hanscom North 
> Airfield project developers to prepare a supplemental DEIR with major changes.
> 
> This does not stop the airport project, but will be a major delay.
> 
> This is good news!
> 
> -Christopher Eliot
> Hanscom Field Advisory Commission, Chair
> -- 