The Validation team weekly report for 2011-03-10 is now available
and can be found at:

  https://wiki.linaro.org/Platform/Validation/Status/2011-03-10

The report is also reproduced in full below.

Regards,
Jamie.
--
Linaro Release Manager   |   Platform Project Manager 

--
 * Period: (20110302-20110309)
 * PM: JamieBennett <jamie.benn...@linaro.org>
 * Past reports : https://wiki.linaro.org/Platform/Validation/Status
 * Burndown information : http://status.linaro.org/linaro-validation.html

== Key Points for wider discussion ==
 * A request for comments on the Debian Django packaging guide has been
   made. Please read and give comments on:
   http://wiki.debian.org/DjangoPackagingDraft.
 * Power Management tests are planned to be integrated into the test
   suite and visualisation tools. The best way to do this is under
   discussion and the team invites more comments.

== Team Highlights ==
 * The Django packaging guideline for Debian was produced and is
   available at http://wiki.debian.org/DjangoPackagingDraft. There are
   discussions ongoing on the debian-python mailing list for feedback.
 * A first (and second) release of the django-debian package was made
   for connecting django database settings to dbconfig-common. This is
   being used on the LAVA project for database integration.
 * Initial discussions have been made to integrate some of the work the
   Power Management Working Group is doing in to abrek (the test-suite
   framework) and launch-control (the test visualisation tool). The ability
   to automatically test and visualise the power consumption on boards will
   take the Validation team around 2-4 weeks to complete.
 * Work continues on LAVA with two new branches containing improvements
   done this week.
 * abrek gained the ability to save bundles at the end of a test run.

== Upcoming Deliverables ==
 * launch-control 0.3c2 deployed on validation.linaro.org

== Risks / Issues ==
 * '''HIGH IMPACT''': Zygmunt's Beagle Board C4 appears to have hardware
   issues (1 week).
 * '''HIGH IMPACT''': The validation scheduler Blueprint continues to
   lag behind with 37 work items to complete (none completed so far) -
   https://launchpad.net/lava/+spec/linaro-n-validation-scheduler (several
   weeks). Discussions are on going to find a way to unblock this project.

== Miscellaneous ==
 * Wiki pages of note this week:
  * http://wiki.debian.org/DjangoPackagingDraft