All, The weekly report for the Linaro Infrastructure team may be found at:- Status report: https://wiki.linaro.org/Platform/Infrastructure/Status/2010-12-09 Burndown chart: This link is awaiting the production of new burndown charts.
The Infrastructure related blueprints from the maverick cycle, of which currently there are 4 active ones (4 from the last report), are showing that there are 8 work items in progress (8 last report), and 11 work items to undertake (11 last report). These are to be moved into the natty cycle if still required. * arm-m-validation-dashboard; no change in status from last report; 3 in progress; 7 to do * arm-m-image-building-console; no change in status from last report; 3 in progress; 3 to do * arm-m-automated-testing-framework; no change in status from last report; 1 in progress; 0 to do * arm-m-testsuites-and-profilers; no change in status from last report; 1 in progress; 1 to do In the natty cycle, the following lists the current active Blueprints, or Blueprints planned and not started. Currently there are 4 active Blueprints (4 from the last report), which are showing that there are 8 work items in progress (7 last report), 41 work items to undertake (46 last report), 2 work items postponed (0 last report) and 8 work items added (all items added last report). * other-linaro-n-improve-linaro-media-create: 5 work items completed (2 last week); 4 work items in progress (3 last week); 8 work items to do (8 last week); 2 work items added this week (2 last week). * other-linaro-n-test-result-display-in-launch-control: 0 work items completed (8 last week); 1 work item in progress (1 last week); 10 work items to do (10 last week); 0 work items added (4 last week) * other-linaro-n-patch-tracking: 0 work item completed (0 last week); 2 work items in progress (2 last week); 9 work items to do (9 last week) * other-linaro-n-image-building: 2 work items in progress (2 last week); 5 work items to do (5 last week); 2 work items postponed (2 last week); 0 work items added (2 last week) * other-linaro-n-continuous-integration: Not started - awaiting a Hudson build server (RT#42278). * other-linaro-n-package-development-tools: Not Started; 9 work items to do Specifics accomplished this week include:- * other-linaro-n-image-building: "4.6 Multiple hwpacks": basically done - needing test and review. * ImproveLinaroMediaCreate: completed the ports to Python of "populate_boot" and "create_partitions" - waiting for review on "create partitions" * Added blueprint/bug links to the LaunchPad API. This is now landed and tested. * Also finished porting the work items tracker to use the launchpad APIPlease let me know if you have any comments or questions. Kind Regards, Ian _______________________________________________ linaro-dev mailing list linaro-dev@lists.linaro.org http://lists.linaro.org/mailman/listinfo/linaro-dev