All,

The weekly report for the Linaro Infrastructure team may be found at:-
Status report:
https://wiki.linaro.org/Platform/Infrastructure/Status/2010-12-09
Burndown chart: This link is awaiting the production of new burndown charts.

The Infrastructure related blueprints from the maverick cycle, of which
currently there are 4 active ones (4 from the last report), are showing
that there are 8 work items in progress (8 last report), and 11 work
items to undertake (11 last report). These are to be moved into the
natty cycle if still required.

* arm-m-validation-dashboard; no change in status from last report; 3 in
progress; 7 to do
* arm-m-image-building-console; no change in status from last report; 3
in progress; 3 to do
* arm-m-automated-testing-framework; no change in status from last
report; 1 in progress; 0 to do
* arm-m-testsuites-and-profilers; no change in status from last report;
1 in progress; 1 to do

In the natty cycle, the following lists the current active Blueprints,
or Blueprints planned and not started. Currently there are 4 active
Blueprints (4 from the last report), which are showing that there are 8
work items in progress (7 last report), 41 work items to undertake (46
last report), 2 work items postponed (0 last report) and 8 work items
added (all items added last report).

  * other-linaro-n-improve-linaro-media-create: 5 work items completed
(2 last week); 4 work items in progress (3 last week); 8 work items to
do (8 last week); 2 work items added this week (2 last week).
  * other-linaro-n-test-result-display-in-launch-control: 0 work items
completed (8 last week); 1 work item in progress (1 last week); 10 work
items to do (10 last week); 0 work items added (4 last week)
  * other-linaro-n-patch-tracking: 0 work item completed (0 last week);
2 work items in progress (2 last week); 9 work items to do (9 last week)
 * other-linaro-n-image-building: 2 work items in progress (2 last
week); 5 work items to do (5 last week); 2 work items postponed (2 last
week); 0 work items added (2 last week)
 * other-linaro-n-continuous-integration: Not started - awaiting a
Hudson build server (RT#42278).
 * other-linaro-n-package-development-tools: Not Started; 9 work items to do

Specifics accomplished this week include:-

 * other-linaro-n-image-building: "4.6 Multiple hwpacks":  basically
done - needing test and review.
 * ImproveLinaroMediaCreate: completed the ports to Python of
"populate_boot" and "create_partitions" - waiting for review on "create
partitions"
 * Added blueprint/bug links to the LaunchPad API. This is now landed
and tested.
 * Also finished porting the work items tracker to use the launchpad
APIPlease let me know if you have any comments or questions.

Kind Regards,


Ian