The weekly report for the Linaro Infrastructure team may be found at:-
Status report: https://wiki.linaro.org/Platform/Infrastructure/Status/2010-12-02
Burndown chart: This link is awaiting the production of new burndown charts.

The Infrastructure related blueprints from the maverick cycle, of which 
currently there are 4 active ones (4 from the last report), are showing that 
there are 8 work items in progress (8 last report), and 11 work items to 
undertake (11 last report). These are to be moved into the natty cycle if still 
required.

 * arm-m-validation-dashboard;        0 work items completed since last report; 
3 in progress;    7 to do
 * arm-m-image-building-console;      0 work items completed since last report; 
3 in progress;    3 to do 
 * arm-m-automated-testing-framework;  no change in status from last report; 1 
in progress;    0 to do
 * arm-m-testsuites-and-profilers;    no change in status from last report; 1 
in progress;    1 to do

In the natty cycle, the following lists the current active Blueprints, or 
Blueprints planned and not started. Currently there are 4 active Blueprints (4 
from the last report), which are showing that there are 8 work items in 
progress (7 last report), 41 work items to undertake (46 last report), 2 work 
items postponed (0 last report) and 8 work items added (all items added last 
report).

 * other-linaro-n-improve-linaro-media-create:  2 work items completed; 3 work 
items in progress; 8 work items to do; 2 work items added.
 * other-linaro-n-test-result-display-in-launch-control:        8 work item 
completed; 1 work item in progress; 10 work items to do; 4 work items added
 * other-linaro-n-patch-tracking:       0 work item completed; 2 work items in 
progress; 9 work items to do
 * other-linaro-n-image-building: 2 work items in progress; 5 work items to do; 
2 work items postponed; 2 work items added
 * other-linaro-n-continuous-integration:       Not started - awaiting a Hudson 
build server (RT#42278).
 * other-linaro-n-package-development-tools: Not Started; 9 work items to do

Specifics accomplished this week include:-

  * Offspring (which used to be known as LexBuilder) has now been open sourced.
  * other-linaro-n-image-building: progress being made on hwpacks
  * ImproveLinaroMediaCreate: the ports of "ensure_command" and 
"unpack_binary_tarball" to Python have been completed.

Please let me know if you have any comments or questions.

Kind Regards,


Ian